3921 W SUNSET BLVD 201 90029
Certificate Information: 3921 W SUNSET BLVD 201 90029
- Application / Permit
- 20016-10000-32233
- Plan Check / Job No.
- B20LA23149
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- OFFICE TENANT IMPROVEMENT OF AN EXISTING TWO STORY BUILDING. WORK TO BE DONE ON 2ND FLOOR. MINOR DEMO, NEW PARTITIONS, NEW DOORS, AND FINISHES. NEW OFFICE SPACES TO INCLUDE NEW SMAL SINKS FOR SANITARY PURPOSES. NO CHANGE OF USE
- Permit Issued
- Issued on 2/26/2021
- Issuing Office
- Current Status
- Permit Finaled on 4/22/2021
Permit Application Status History
| Submitted | 12/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | JOE VO |
| Corrections Issued | 12/27/2020 | JOE VO |
| Quality Review Completed | 1/12/2021 | KEN GILL |
| Disabled Access Plans Picked Up | 2/4/2021 | APPLICANT |
| Green Plans Picked Up | 2/11/2021 | APPLICANT |
| Plan Check Approved | 2/22/2021 | JOE VO |
| Issued | 2/26/2021 | APPLICANT |
| Building Plans Picked Up | 3/2/2021 | APPLICANT |
| Permit Finaled | 4/22/2021 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Green Code | Cleared | 1/14/2021 | AARON COSTA |
| DAS Clearance | Cleared | 2/4/2021 | JOE VO |
Contact Information
| Architect | Milford,, Brian T; Lic. No.: C33430 | 941 WALNUT AVENUE WALNUT CREEK, CA 94598 |
| Contractor | Precise General Contractor Inc; Lic. No.: 883707-B | 8504 FIRESTONE BLVD STE 302 DOWNEY, CA 90241 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 3/4/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Drywall Nailing | 3/11/2021 | Approved | RUSSELL BONVOULOIR |
| Drywall Nailing | 3/22/2021 | Approved | RUSSELL BONVOULOIR |
| Final | 4/8/2021 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Green Building Final | 4/8/2021 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 4/8/2021 | SGSOV Approved | RUSSELL BONVOULOIR |
| Smoke Detectors | 4/8/2021 | Approved | RUSSELL BONVOULOIR |
| Final | 4/13/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Green Building Final | 4/13/2021 | Approved | RUSSELL BONVOULOIR |
| Final | 4/22/2021 | Permit Finaled | RUSSELL BONVOULOIR |