1505 N ALLESANDRO ST 90026
Certificate Information: 1505 N ALLESANDRO ST 90026
- Application / Permit
- 20016-10000-32230
- Plan Check / Job No.
- B20LA23145
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR RENOVATION AND ADDITION TO (E) 1-STORY SFD.
- Permit Issued
- Issued on 4/30/2021
- Issuing Office
- Current Status
- CofO Issued on 12/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2020 | TSE MING HUANG |
| Corrections Issued | 12/22/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 1/15/2021 | LUKE GONZALES |
| Plan Check Approved | 2/25/2021 | SAMUEL GONZALEZ |
| Issued | 4/30/2021 | APPLICANT |
| Building Plans Picked Up | 5/3/2021 | APPLICANT |
| CofO in Progress | 11/21/2023 | THOMAS LOGRASSO |
| CofO Issued | 12/4/2023 | DEROLD HAUFF |
| Permit Finaled | 12/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/10/2021 | VASIL MIHALEV |
Contact Information
| Architect | , ; Lic. No.: C36682 | LOS ANGELES, CA 90004 |
| Architect | Asamoah,, B Kwesi; Lic. No.: C36558 | 850 ROSE AVENUE VENICE, CA 90291 |
| Contractor | Oakwood Construction; Lic. No.: 762828-B | 4955 E HUNTER AVE ANAHEIM, CA 92807 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/18/2021 | Corrections Issued | OSVALDO PARAMO |
| Pre-Inspection | 7/22/2021 | Corrections Issued | THOMAS LOGRASSO |
| Pre-Inspection | 11/30/2021 | Partial Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 12/8/2021 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/8/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 2/23/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/10/2022 | Corrections Issued | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 5/19/2022 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/11/2022 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/11/2022 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 8/11/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/11/2022 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/6/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 9/6/2022 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 9/6/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 9/6/2022 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 9/28/2022 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 10/17/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 12/6/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/19/2022 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 12/19/2022 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 12/19/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 12/19/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 12/19/2022 | Approved | THOMAS LOGRASSO |
| Final | 8/23/2023 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/23/2023 | Approved | THOMAS LOGRASSO |
| Green Building Final | 8/23/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 8/23/2023 | SGSOV Not Ready | THOMAS LOGRASSO |
| Smoke Detectors | 8/23/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 10/30/2023 | Approved | THOMAS LOGRASSO |
| Final | 10/30/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 10/30/2023 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 10/30/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 10/30/2023 | Approved | THOMAS LOGRASSO |
| Final | 11/9/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 11/20/2023 | OK to Issue CofO | THOMAS LOGRASSO |