4328 S CHASE AVE 90066
Certificate Information: 4328 S CHASE AVE 90066
- Application / Permit
- 20016-10000-32196
- Plan Check / Job No.
- B20LA23125
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior renovation of 1-story SFD: Remodel kitchen. Add new beam. Relocation of (E) Wall opennings within (E) Building footprint, moving of one (E) Exterior Window.
- Permit Issued
- Issued on 1/6/2021
- Issuing Office
- Current Status
- Permit Finaled on 9/9/2021
Permit Application Status History
| Submitted | 12/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2020 | JESSE JIMENEZ |
| Plan Check Approved | 12/23/2020 | JESSE JIMENEZ |
| Issued | 1/6/2021 | APPLICANT |
| Building Plans Picked Up | 1/8/2021 | APPLICANT |
| Permit Finaled | 9/9/2021 | ENRIQUE MIRELES |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Golden Age Builders; Lic. No.: 1040171-B | 7494 SANTA MONICA BLVD 201 LOS ANGELES, CA 90046 |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/2/2021 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 2/25/2021 | Not Ready for Inspection | DAVID HEINE |
| ELECTRICAL-Rough | 2/25/2021 | Corrections Issued | DAVID HEINE |
| HVAC-Rough | 2/25/2021 | Approved | DAVID HEINE |
| PLUMBING-Rough | 2/25/2021 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 3/2/2021 | Corrections Issued | DAVID HEINE |
| BUILDING-Rough-Frame | 3/4/2021 | Approved | DAVID HEINE |
| Insulation | 3/4/2021 | Approved | DAVID HEINE |
| Drywall Nailing | 3/16/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 4/20/2021 | Partial Inspection | PIERRE VEGA |
| Interior/Exterior Lathing | 5/6/2021 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 5/6/2021 | Partial Inspection | SHAVONNE ESPINOZA |
| Final | 8/27/2021 | Corrections Issued | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 8/27/2021 | SGSOV Not Ready | ENRIQUE MIRELES |
| Smoke Detectors | 8/27/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 9/9/2021 | Permit Finaled | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 9/9/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 9/9/2021 | Approved | ENRIQUE MIRELES |