1400 N ORANGE DR 90028

Certificate Information: 1400 N ORANGE DR 90028

Application / Permit
20016-10000-32164
Plan Check / Job No.
B20LA23102
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL OF SFD AND CONVERT PORTION OF EXISTING SFD TO ADU (604 SF) PER CA GOVT CODE 65852.2(E)(1)(A) Comply with Department Order effective date 07/06/2020. CEIS Case Numberis 900084.
Permit Issued
Issued on 11/5/2021
Issuing Office
Current Status
CofO Issued on 10/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/14/2020 APPLICANT
Assigned to Plan Check Engineer 1/7/2021 STARR CHEN
Corrections Issued 1/9/2021 STARR CHEN
Quality Review Completed 1/15/2021 HERNAN ARREOLA
Building Plans Picked Up 1/20/2021 APPLICANT
Applicant returned to address corrections 4/23/2021 STARR CHEN
Applicant returned to address corrections 7/15/2021 STARR CHEN
Applicant returned to address corrections 8/27/2021 STARR CHEN
Applicant returned to address corrections 9/2/2021 STARR CHEN
Applicant returned to address corrections 9/17/2021 STARR CHEN
Applicant returned to address corrections 9/30/2021 STARR CHEN
Plan Check Approved 10/7/2021 STARR CHEN
Issued 11/5/2021 APPLICANT
CofO in Progress 4/28/2022 BRIAN SULLIVAN
Permit Finaled 10/20/2022 DEROLD HAUFF
CofO Issued 10/20/2022 DEROLD HAUFF
Permit Finaled 10/20/2022 DEROLD HAUFF

Permit Application Clearance Information

Historic Resource Verification Cleared 3/25/2021 MICAELA TORRES-GIL
Address approval Cleared 4/6/2021 WALLIE JONG
Permit Cleared 4/6/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 4/6/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/7/2021 WALLIE JONG
Sewer availability Cleared 4/7/2021 WALLIE JONG
Trees in Parkway Cleared 4/14/2021 JOHN KIM
Redevelopment Project Area Cleared 7/19/2021 GISELLE CORELLA

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 11/10/2021 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 11/23/2021 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 11/30/2021 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 11/30/2021 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 11/30/2021 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 12/6/2021 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 12/6/2021 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 12/9/2021 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 12/9/2021 Corrections Issued BRIAN SULLIVAN
PLUMBING-Rough 12/9/2021 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 12/14/2021 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 12/14/2021 Partial Approval RAUL BARAJAS
PLUMBING-Rough 12/14/2021 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 12/17/2021 Approved DANIEL GONZALEZ
Shower Pan 12/17/2021 Approved DANIEL GONZALEZ
BUILDING-Rough-Frame 12/22/2021 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 12/22/2021 Approved BRIAN SULLIVAN
PLUMBING-Rough 12/27/2021 Approved STUART CHAPMAN
Wood Frame 12/27/2021 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 12/30/2021 Not Ready for Inspection JOSEPH MCGARRY
Wood Frame 12/30/2021 Not Ready for Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 1/3/2022 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 1/5/2022 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 1/5/2022 Approved BRIAN SULLIVAN
HVAC-Rough 1/5/2022 Not Ready for Inspection BRIAN SULLIVAN
Interior/Exterior Lathing 1/5/2022 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 1/13/2022 Partial Approval BRIAN SULLIVAN
Drywall Nailing 1/13/2022 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 1/24/2022 Approved BRIAN SULLIVAN
Drywall Nailing 1/24/2022 Approved BRIAN SULLIVAN
HVAC-Rough 1/24/2022 Approved BRIAN SULLIVAN
Special/Order Compliance 1/24/2022 Corrections Issued BRIAN SULLIVAN
Service/Power Release 1/31/2022 Not Ready for Inspection BRIAN SULLIVAN
Service/Power Release 2/3/2022 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Final 3/15/2022 No Access for Inspection BRIAN SULLIVAN
Gas Test 3/15/2022 No Access for Inspection BRIAN SULLIVAN
HVAC-Final 3/15/2022 No Access for Inspection BRIAN SULLIVAN
PLUMBING-Final 3/15/2022 No Access for Inspection BRIAN SULLIVAN
Service/Power Release 3/15/2022 No Access for Inspection BRIAN SULLIVAN
ELECTRICAL-Final 3/30/2022 Not Ready for Inspection BRIAN SULLIVAN
Final 3/30/2022 Not Ready for Inspection BRIAN SULLIVAN
Gas Test 3/30/2022 Approved BRIAN SULLIVAN
HVAC-Final 3/30/2022 Corrections Issued BRIAN SULLIVAN
PLUMBING-Final 3/30/2022 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 3/30/2022 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 3/30/2022 Not Ready for Inspection BRIAN SULLIVAN
Smoke Detectors 3/30/2022 Approved BRIAN SULLIVAN
ELECTRICAL-Final 4/14/2022 Approved BRIAN SULLIVAN
Final 4/14/2022 Corrections Issued BRIAN SULLIVAN
HVAC-Final 4/14/2022 Approved BRIAN SULLIVAN
PLUMBING-Final 4/14/2022 Approved BRIAN SULLIVAN
Service/Power Release 4/14/2022 Not Ready for Inspection BRIAN SULLIVAN
Final 4/28/2022 OK to Issue CofO BRIAN SULLIVAN
Service/Power Release 4/28/2022 Approved BRIAN SULLIVAN