7432 N RESEDA BLVD 91335

Certificate Information: 7432 N RESEDA BLVD 91335

Application / Permit
20016-10000-32151
Plan Check / Job No.
B20LA23085
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
CHANGE OF USE/OCCUPANCY FROM TRANSIENT MOTEL TO NON-TRANSIENT HOTEL. NFPA 13R FIRE SPRINKLERS REQUIRED. INTERIOR RENOVATIONS INCLUDING (8) UNITS TO RECEIVE ACCESSIBILITY UPGRADES, (4) UNITS TO BE RENOVATED FOR THE VUSUALLY AND AUDITORY IMPAIRED.
Permit Issued
Issued on 8/18/2021
Issuing Office
Current Status
CofO Issued on 8/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/14/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 KEVIN MORALES
Building Plans Picked Up 12/28/2020 APPLICANT
Corrections Issued 12/30/2020 KEVIN MORALES
Quality Review Completed 1/4/2021 EUGENE BARBEAU
Green Plans Picked Up 3/5/2021 APPLICANT
Plan Check Approved 4/14/2021 KEVIN MORALES
Issued 8/18/2021 APPLICANT
CofO in Progress 7/31/2023 BRIAN KELLY
Permit Finaled 8/3/2023 JEFFREY DURAN
CofO Issued 8/3/2023 JEFFREY DURAN
Permit Finaled 8/3/2023 JEFFREY DURAN

Permit Application Clearance Information

"Q" conditions Cleared 1/21/2021 MARITZA PRZEKOP
Supp. Use District POD/CDO/TDO Cleared 1/21/2021 MARITZA PRZEKOP
ZA Case Cleared 1/21/2021 MARITZA PRZEKOP
Eng Process Fee Ord 176,300 Cleared 2/3/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/19/2021 JOHN TRIANTAFYLLOS
City owned building/parcel Cleared 2/26/2021 DANIEL TARICA
Fire Marshal Fire Life Safety Cleared 3/4/2021 MENOA AGHAJANI
Miscellaneous Cleared 3/9/2021 MARITZA PRZEKOP
DAS Clearance Cleared 4/9/2021 SHINE LIN
Green Code Cleared 4/13/2021 KEVIN MORALES

Contact Information

Contractor Belfor Usa Group Inc; Lic. No.: 810553-B 185 OAKLAND AVENUE STE 150      BIRMINGHAM, MI 48009

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/1/2022 Corrections Issued DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 5/10/2022 Partial Inspection ANDREW DORSO
Pre-Inspection 5/20/2022 Corrections Issued ANDREW DORSO
Excavation/Setback/Form/Re-Bar 5/26/2022 Corrections Issued DANIEL VARNUM
Pre-Inspection 5/26/2022 Partial Inspection DANIEL VARNUM
Insulation 6/1/2022 Partial Inspection ANDREW DORSO
Light Gage Steel Frame 6/1/2022 Not Ready for Inspection ANDREW DORSO
Light Gage Steel Frame 6/2/2022 Not Ready for Inspection DANIEL VARNUM
Wood Frame 6/2/2022 Not Ready for Inspection DANIEL VARNUM
Drywall Nailing 6/6/2022 Not Ready for Inspection DANIEL VARNUM
Wood Frame 6/6/2022 Partial Approval DANIEL VARNUM
Drywall Nailing 6/7/2022 Partial Approval DANIEL VARNUM
Insulation 6/21/2022 Not Ready for Inspection KENNETH ROBERTS
Light Gage Steel Frame 6/21/2022 Not Ready for Inspection KENNETH ROBERTS
Wood Frame 6/21/2022 Not Ready for Inspection KENNETH ROBERTS
Insulation 6/24/2022 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 6/24/2022 Partial Approval DANIEL VARNUM
Wood Frame 6/24/2022 Partial Approval DANIEL VARNUM
Drywall Nailing 7/1/2022 Partial Approval DANIEL VARNUM
Final 8/11/2022 Partial Inspection DANIEL VARNUM
Green Building Final 8/11/2022 Not Ready for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 8/11/2022 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 8/11/2022 Partial Approval DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 8/15/2022 Not Ready for Inspection DANIEL VARNUM
Footing/Foundation/Slab 8/15/2022 Approved DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 9/23/2022 Partial Inspection ANDREW DORSO
Excavation/Setback/Form/Re-Bar 9/27/2022 Corrections Issued ANDREW DORSO
Pre-Inspection 10/6/2022 Partial Inspection DANIEL VARNUM
Special/Order Compliance 10/20/2022 Partial Inspection DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 11/1/2022 Partial Inspection ANDREW DORSO
Insulation 12/7/2022 Partial Inspection BRIAN KELLY
Light Gage Steel Frame 12/7/2022 Approved BRIAN KELLY
Insulation 12/8/2022 Partial Inspection BRIAN KELLY
Drywall Nailing 12/13/2022 Partial Inspection BRIAN KELLY
Drywall Nailing 12/19/2022 Partial Inspection BRIAN KELLY
Drywall Nailing 12/22/2022 Partial Inspection BRIAN KELLY
Insulation 12/22/2022 Partial Inspection BRIAN KELLY
Wood Frame 12/22/2022 Partial Inspection BRIAN KELLY
Drywall Nailing 1/4/2023 Partial Approval KENNETH ROBERTS
Light Gage Steel Frame 1/13/2023 Approved BRIAN KELLY
Final 2/3/2023 Not Ready for Inspection BRIAN KELLY
Green Building Final 2/3/2023 Not Ready for Inspection BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 2/3/2023 SGSOV Not Ready BRIAN KELLY
Smoke Detectors 2/3/2023 Not Ready for Inspection BRIAN KELLY
Final 2/9/2023 Partial Approval BRIAN KELLY
Green Building Final 2/9/2023 Partial Approval BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 2/9/2023 SGSOV Not Ready BRIAN KELLY
Smoke Detectors 2/9/2023 Partial Approval BRIAN KELLY
Light Gage Steel Frame 3/21/2023 Not Ready for Inspection BRIAN KELLY
Insulation 3/24/2023 Not Ready for Inspection KENNETH ROBERTS
Light Gage Steel Frame 3/24/2023 Partial Approval KENNETH ROBERTS
Drywall Nailing 3/29/2023 Partial Approval BRIAN KELLY
Drywall Nailing 3/30/2023 Not Ready for Inspection BRIAN KELLY
Insulation 3/30/2023 Not Ready for Inspection BRIAN KELLY
Light Gage Steel Frame 3/30/2023 Not Ready for Inspection BRIAN KELLY
Drywall Nailing 3/31/2023 Partial Inspection BRIAN KELLY
Insulation 5/23/2023 Approved BRIAN KELLY
Light Gage Steel Frame 5/23/2023 Approved BRIAN KELLY
Drywall Nailing 5/26/2023 Approved BRIAN KELLY
Final 7/21/2023 Not Ready for Inspection BRIAN KELLY
Green Building Final 7/21/2023 Not Ready for Inspection BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 7/21/2023 SGSOV Not Ready BRIAN KELLY
Smoke Detectors 7/21/2023 Not Ready for Inspection BRIAN KELLY
Pre-Inspection 7/25/2023 Partial Approval BRIAN KELLY
Final 7/28/2023 OK to Issue CofO BRIAN KELLY
Green Building Final 7/28/2023 Approved BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 7/28/2023 SGSOV Approved BRIAN KELLY
Smoke Detectors 7/28/2023 Approved BRIAN KELLY