17320 W TIARA ST 91316
Certificate Information: 17320 W TIARA ST 91316
- Application / Permit
- 20016-10000-32077
- Plan Check / Job No.
- B20LA23025
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL AND ADDITION
- Permit Issued
- Issued on 3/9/2021
- Issuing Office
- Current Status
- CofO Issued on 12/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2020 | SINA KHOSRAVI |
| Corrections Issued | 12/18/2020 | SINA KHOSRAVI |
| Applicant returned to address corrections | 1/19/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 2/9/2021 | TSE MING HUANG |
| Plan Check Approved | 3/8/2021 | RICARDO RAMIREZ |
| Issued | 3/9/2021 | APPLICANT |
| Building Plans Picked Up | 3/11/2021 | APPLICANT |
| CofO in Progress | 11/24/2021 | SEAN HAUPT |
| CofO Issued | 12/3/2021 | MICHAEL SMITH |
| Permit Finaled | 12/3/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 2/2/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Golden Age Construction Inc; Lic. No.: 1040171-B | 7494 SANTA MONICA BLVD 201 LOS ANGELES, CA 90046 |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/16/2021 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 4/16/2021 | Not Ready for Inspection | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 4/23/2021 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 4/23/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 5/5/2021 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 5/5/2021 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 5/24/2021 | Partial Approval | STEVEN BACK |
| Gas Test | 5/24/2021 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 5/24/2021 | Partial Approval | STEVEN BACK |
| Insulation | 5/28/2021 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2021 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 6/30/2021 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 6/30/2021 | Partial Approval | STEVEN BACK |
| HVAC-Rough | 6/30/2021 | Approved | STEVEN BACK |
| PLUMBING-Rough | 6/30/2021 | Approved | STEVEN BACK |
| Deputy Wood Construction | 7/1/2021 | Conditional Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 7/8/2021 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 7/8/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2021 | Approved | STEVEN BACK |
| Green Building Rough | 7/8/2021 | Not Ready for Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 7/14/2021 | Approved | RYAN SALAZAR |
| Shower Pan | 7/14/2021 | Corrections Issued | RYAN SALAZAR |
| Green Building Rough | 7/20/2021 | Approved | RYAN SALAZAR |
| Insulation | 7/20/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/20/2021 | Approved | RYAN SALAZAR |
| Shower Pan | 7/20/2021 | Approved | RYAN SALAZAR |
| Drywall Nailing | 7/23/2021 | Approved | RYAN SALAZAR |
| Final | 9/24/2021 | Corrections Issued | STEVEN BACK |
| Green Building Final | 9/24/2021 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 9/24/2021 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 9/24/2021 | Approved | STEVEN BACK |
| Final | 11/2/2021 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Final | 11/2/2021 | Not Ready for Inspection | SEAN HAUPT |
| Final | 11/22/2021 | Conditional Approval | SEAN HAUPT |
| Green Building Final | 11/22/2021 | Approved | SEAN HAUPT |