4339 1/2 N ALLOTT AVE 91423

Certificate Information: 4339 1/2 N ALLOTT AVE 91423

Application / Permit
20016-10000-32040
Plan Check / Job No.
B20LA23002
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing 20x20 detached garage into a new ADU.
Permit Issued
Issued on 11/8/2021
Issuing Office
Current Status
CofO Issued on 10/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2020 APPLICANT
Assigned to Plan Check Engineer 1/4/2021 JOE VO
Corrections Issued 1/4/2021 JOE VO
Applicant returned to address corrections 8/3/2021 JOE VO
Applicant returned to address corrections 8/23/2021 JOE VO
Plan Check Approved 9/23/2021 JOE VO
Issued 11/8/2021 APPLICANT
CofO in Progress 9/26/2024 JUAN VALENZUELA
Permit Finaled 10/8/2024 DANIEL ORRANTE
CofO Issued 10/8/2024 DANIEL ORRANTE
Permit Finaled 10/8/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/28/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 4/28/2021 JOHN TRIANTAFYLLOS
Certificate of Compliance Cleared 4/29/2021 LAUREN PADICK
Eng Process Fee Ord 176,300 Cleared 6/7/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/18/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 7/15/2024 Approved MISAEL ESPARZA
PLUMBING-Rough 7/15/2024 Partial Approval MISAEL ESPARZA
Sewer 7/15/2024 Approved MISAEL ESPARZA
Underground Mechanical 7/15/2024 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 7/25/2024 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 7/25/2024 Corrections Issued JACK KARGODORIAN
Green Building Rough 7/25/2024 Approved JACK KARGODORIAN
HVAC-Rough 7/25/2024 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Rough 7/25/2024 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 8/5/2024 Corrections Issued MISAEL ESPARZA
Deputy Wood Construction 8/5/2024 Approved MISAEL ESPARZA
ELECTRICAL-Rough 8/5/2024 Conditional Approval MISAEL ESPARZA
Interior/Exterior Lathing 8/5/2024 Not Ready for Inspection MISAEL ESPARZA
Shower Pan 8/5/2024 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 8/5/2024 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 8/9/2024 Approved MISAEL ESPARZA
HVAC-Rough 8/9/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 8/9/2024 Partial Approval MISAEL ESPARZA
Insulation 8/12/2024 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 8/12/2024 Approved MICHAEL CORTEZ
Drywall Nailing 8/14/2024 Approved MICHAEL CORTEZ
BUILDING-Rough-Frame 9/16/2024 Approved MISAEL ESPARZA
Final 9/16/2024 Corrections Issued MISAEL ESPARZA
Green Building Final 9/16/2024 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/16/2024 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 9/16/2024 Approved MISAEL ESPARZA
ELECTRICAL-Final 9/19/2024 Approved MISAEL ESPARZA
Final 9/19/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 9/19/2024 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/19/2024 No Access for Inspection MISAEL ESPARZA
Final 9/26/2024 OK to Issue CofO MISAEL ESPARZA
Green Building Final 9/26/2024 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/26/2024 SGSOV Not Ready MISAEL ESPARZA