14340 W ADDISON ST 1-45 91423
Certificate Information: 14340 W ADDISON ST 1-45 91423
- Application / Permit
- 20016-10000-31940
- Plan Check / Job No.
- B20LA22916
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- Convert exisiting recreatiom room and portion of existing laundrt room to ADU and leasing office, part of existing apartment building.
- Permit Issued
- Issued on 6/10/2022
- Issuing Office
- Current Status
- CofO Issued on 7/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | JOE VO |
| Corrections Issued | 12/25/2020 | JOE VO |
| Quality Review Completed | 1/12/2021 | KEN GILL |
| Applicant returned to address corrections | 2/23/2022 | JOE VO |
| Plan Check Approved | 6/6/2022 | JOE VO |
| Issued | 6/10/2022 | APPLICANT |
| Building Plans Picked Up | 12/7/2022 | APPLICANT |
| CofO in Progress | 7/24/2025 | ANDREW DORSO |
| CofO Issued | 7/28/2025 | JEFFREY DURAN |
| Permit Finaled | 7/28/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 3/11/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/11/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 5/24/2021 | KURT CORRAL |
| Tenant Habitability Plan | Cleared | 5/23/2022 | RICARDO BOHORQUEZ |
| DAS Clearance | Cleared | 6/6/2022 | JOE VO |
Contact Information
| Contractor | Jang Construction Management; Lic. No.: 1049329-B | 1249 KOLLE AVE SOUTH PASADENA, CA 91030 |
| Engineer | Bell,, William Andrew; Lic. No.: C88870 | 550 DEEP VALLEY DR STE 273 ROLLING HILLS ESTATES, CA 90274 |
Inspector Information
| SEAN GRIFFITH, (818) 374-1102 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/26/2023 | Conditional Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 1/30/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Special/Order Compliance | 1/30/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 2/2/2023 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 2/2/2023 | Corrections Issued | ANDREW DORSO |
| Deputy Drilled-In Anchors | 2/24/2023 | Conditional Approval | STEVEN LEVITT |
| Deputy Drilled-In Anchors | 6/20/2023 | Conditional Approval | STEVEN LEVITT |
| Wood Frame | 6/29/2023 | Approved | STEVEN LEVITT |
| Insulation | 7/10/2023 | Approved | STEVEN LEVITT |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2023 | Approved | STEVEN LEVITT |
| Drywall Nailing | 7/21/2023 | Approved | STEVEN LEVITT |
| Interior/Exterior Lathing | 7/21/2023 | Approved | STEVEN LEVITT |
| Interior/Exterior Lathing | 8/4/2023 | Approved | STEVEN LEVITT |
| Final | 9/25/2023 | Not Ready for Inspection | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 9/25/2023 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 9/25/2023 | Not Ready for Inspection | ANDREW DORSO |
| Final | 9/27/2023 | Conditional Approval | STEVEN LEVITT |
| Smoke Detectors | 9/27/2023 | Approved | STEVEN LEVITT |
| Final | 7/24/2025 | OK to Issue CofO | ANDREW DORSO |