Pre-Inspection
|
8/23/2023
|
Approved
|
KATY RAMIREZ
|
|
Deputy Drilled-In Anchors
|
10/5/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Deputy Drilled-In Anchors
|
10/11/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Deputy Drilled-In Anchors
|
10/12/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Deputy Drilled-In Anchors
|
10/13/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Deputy Drilled-In Anchors
|
10/16/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Deputy Drilled-In Anchors
|
10/17/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Deputy Drilled-In Anchors
|
10/18/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Deputy Drilled-In Anchors
|
10/19/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Deputy Drilled-In Anchors
|
10/20/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Deputy Drilled-In Anchors
|
10/23/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Drilled-In Anchors
|
10/24/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Drilled-In Anchors
|
10/25/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Drilled-In Anchors
|
10/27/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Reinforced Concrete Frame
|
10/27/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Deputy Reinf. Concrete
|
10/30/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Reinforced Concrete Frame
|
10/30/2023
|
Not Ready for Inspection
|
KATY RAMIREZ
|
|
Special/Order Compliance
|
10/30/2023
|
Partial Approval
|
RICARDO ROBLES
|
|
Deputy Reinf. Concrete
|
10/31/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Reinforced Concrete Frame
|
10/31/2023
|
Partial Inspection
|
KATY RAMIREZ
|
|
Deputy Reinf. Concrete
|
11/1/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Deputy Reinf. Concrete
|
11/2/2023
|
Conditional Approval
|
RAMAZANALI ALMASI
|
|
Reinforced Concrete Frame
|
11/2/2023
|
Partial Approval
|
RICARDO ROBLES
|
|
Deputy Reinf. Concrete
|
11/3/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Deputy Reinf. Concrete
|
11/6/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
11/8/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Deputy Drilled-In Anchors
|
11/9/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Reinforced Concrete Frame
|
11/13/2023
|
Not Ready for Inspection
|
JEROME BLACKWOOD
|
|
Reinforced Concrete Frame
|
11/14/2023
|
Partial Approval
|
KATY RAMIREZ
|
|
Deputy Reinf. Concrete
|
11/20/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Reinforced Concrete Frame
|
11/20/2023
|
Partial Approval
|
KATY RAMIREZ
|
|
Deputy Reinf. Concrete
|
12/1/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Deputy Reinf. Concrete
|
12/5/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Reinforced Concrete Frame
|
12/5/2023
|
Not Ready for Inspection
|
KATY RAMIREZ
|
|
Deputy Reinf. Concrete
|
12/6/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Deputy Reinf. Concrete
|
12/7/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Excavation/Setback/Form/Re-Bar
|
12/7/2023
|
Partial Approval
|
KATY RAMIREZ
|
|
Deputy Reinf. Concrete
|
12/8/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Drilled-In Anchors
|
12/19/2023
|
No Access for Inspection
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
12/20/2023
|
Conditional Approval
|
KATY RAMIREZ
|
|
Excavation/Setback/Form/Re-Bar
|
12/21/2023
|
Partial Approval
|
KATY RAMIREZ
|
|
Drywall Nailing
|
1/2/2024
|
Not Ready for Inspection
|
KATY RAMIREZ
|
|
Light Gage Steel Frame
|
1/2/2024
|
Not Ready for Inspection
|
KATY RAMIREZ
|
|
Deputy Drilled-In Anchors
|
1/17/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Excavation/Setback/Form/Re-Bar
|
1/31/2024
|
Partial Approval
|
KATY RAMIREZ
|
|
Deputy Drilled-In Anchors
|
2/20/2024
|
Partial Approval
|
JACOB MYERS
|
|
Excavation/Setback/Form/Re-Bar
|
2/27/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Reinforced Concrete Frame
|
2/29/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Deputy Drilled-In Anchors
|
3/20/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Excavation/Setback/Form/Re-Bar
|
3/26/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Footing/Foundation/Slab
|
3/26/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Reinforced Concrete Frame
|
4/17/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Reinforced Concrete Frame
|
4/25/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Insulation
|
5/9/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Drywall Nailing
|
5/15/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Deputy Reinf. Concrete
|
5/28/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Reinforced Concrete Frame
|
5/28/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Reinforced Concrete Frame
|
6/14/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Reinforced Concrete Frame
|
6/21/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Deputy Reinf. Concrete
|
7/9/2024
|
Partial Approval
|
JEROME BLACKWOOD
|
|
Deputy Steel/Welding
|
7/9/2024
|
Partial Approval
|
JEROME BLACKWOOD
|
|
Deputy Steel/Welding
|
7/15/2024
|
Partial Approval
|
JEROME BLACKWOOD
|
|
Deputy Drilled-In Anchors
|
8/8/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Drywall Nailing
|
8/26/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Reinforced Concrete Frame
|
8/28/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Light Gage Steel Frame
|
9/3/2024
|
Partial Approval
|
JEROME BLACKWOOD
|
|
Final
|
6/24/2025
|
Partial Approval
|
PAUL BAZERKANIAN
|
|
Green Building Final
|
6/24/2025
|
Approved
|
PAUL BAZERKANIAN
|
|
SGSOV-Seismic Gas S/O Valve
|
6/24/2025
|
SGSOV Approved
|
PAUL BAZERKANIAN
|
|
Smoke Detectors
|
6/24/2025
|
Approved
|
PAUL BAZERKANIAN
|
|
Final
|
7/9/2025
|
Not Ready for Inspection
|
PAUL BAZERKANIAN
|
|
Final
|
9/23/2025
|
Permit Finaled
|
PAUL BAZERKANIAN
|