1345 W 30TH PL 90007
Certificate Information: 1345 W 30TH PL 90007
- Application / Permit
- 20016-10000-31766
- Plan Check / Job No.
- B20LA22778
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING 2 CAR GARAGE AND EXISTING STORAGE TO ACCESSORY DWELLING UNIT, SAME SIZE AND FOOTPRINT PER GCS 65852.2(e)(1)(D) AND LAMC 12.22A.33(c)(d)AND(g) 2 OF 2
- Permit Issued
- Issued on 5/7/2021
- Issuing Office
- Current Status
- CofO Issued on 6/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 12/22/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 12/29/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 1/8/2021 | APPLICANT |
| Applicant returned to address corrections | 3/25/2021 | SERGIO GUTIERREZ |
| Plan Check Approved | 5/7/2021 | SERGIO GUTIERREZ |
| Issued | 5/7/2021 | APPLICANT |
| CofO in Progress | 6/27/2025 | WILLIAM SIERRA |
| Permit Finaled | 6/29/2025 | DEROLD HAUFF |
| CofO Issued | 6/29/2025 | DEROLD HAUFF |
| Permit Finaled | 6/29/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/10/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 2/10/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 2/10/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2021 | RENZ SORIANO |
| ZI | Cleared | 2/18/2021 | TERRI OSBORNE |
| Hydrant and Access approval | Cleared | 2/28/2021 | JEREMY CARTER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chao,, Hong Chuen; Lic. No.: C68688 | 12964 EAST END AVENUE CHINO, CA 91710 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/18/2021 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 5/18/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 5/18/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Sewer | 5/18/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 5/27/2021 | Partial Inspection | SCOTT FINNILA |
| Footing/Foundation/Slab | 5/27/2021 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 5/27/2021 | Partial Inspection | SCOTT FINNILA |
| ELECTRICAL-Rough | 6/7/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 6/7/2021 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 6/7/2021 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 6/7/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 6/11/2021 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/11/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 6/17/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| HVAC-Rough | 6/17/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 6/30/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 6/30/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 6/30/2021 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 7/19/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 7/19/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Gas Test | 7/19/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 7/19/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| METHANE-Rough | 7/19/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 7/27/2021 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 7/28/2021 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 7/28/2021 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2021 | Approved | KATHRYN BUTTERWORTH |
| Gas Test | 7/28/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 7/28/2021 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 7/28/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Rough | 7/28/2021 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 7/30/2021 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 7/30/2021 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 8/4/2021 | Approved | KATHRYN BUTTERWORTH |
| Gas Test | 8/4/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 9/13/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 9/13/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| HVAC-Final | 9/13/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 9/13/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 9/13/2021 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Smoke Detectors | 9/13/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 9/20/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Gas Test | 9/20/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| HVAC-Final | 9/20/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 9/20/2021 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Sewer | 9/20/2021 | Approved | KATHRYN BUTTERWORTH |
| Smoke Detectors | 9/20/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Underground Mechanical | 9/20/2021 | Approved | KATHRYN BUTTERWORTH |
| Final | 9/27/2021 | Conditional Approval | HORACE FULTZ |
| Gas Test | 9/27/2021 | Approved | HORACE FULTZ |
| HVAC-Final | 9/27/2021 | Approved | HORACE FULTZ |
| Smoke Detectors | 9/27/2021 | Approved | HORACE FULTZ |
| ELECTRICAL-Final | 6/26/2025 | Approved | WILLIAM SIERRA |
| Final | 6/26/2025 | OK to Issue CofO | WILLIAM SIERRA |
| HVAC-Final | 6/26/2025 | Approved | WILLIAM SIERRA |
| PLUMBING-Final | 6/26/2025 | Approved | WILLIAM SIERRA |