1065 S NORTON AVE 90019
Certificate Information: 1065 S NORTON AVE 90019
- Application / Permit
- 20016-10000-31726
- Plan Check / Job No.
- B20LA22747
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: Soft Story retrofit based on mandatory ordinance using shear walls. ADU WILL BE UNDER 20016-10000-31445.
- Permit Issued
- Issued on 5/6/2021
- Issuing Office
- Current Status
- CofC Issued on 1/13/2025
Permit Application Status History
| Submitted | 12/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | VARAND SARKISIAN |
| Corrections Issued | 1/21/2021 | VARAND SARKISIAN |
| Quality Review Completed | 1/26/2021 | DAVID CHANG |
| Applicant returned to address corrections | 2/23/2021 | VARAND SARKISIAN |
| Plan Check Approved | 3/8/2021 | VARAND SARKISIAN |
| Issued | 5/6/2021 | APPLICANT |
| OK for CofC | 8/9/2022 | DARRYL ARNOLD |
| CofC Issued | 1/13/2025 | WINSTON DUNNING |
Permit Application Clearance Information
| HPOZ | Cleared | 1/29/2021 | AMANDA KAINER |
| Tenant Habitability Plan | Cleared | 4/27/2021 | MICHAEL SOTO |
Contact Information
| Architect | Hanna,, Remon; Lic. No.: C36271 | 26030 SANDBURG PL STEVENSON RANCH, CA 91381 |
| Contractor | Adu Concepts; Lic. No.: 1018294-B | 18375 VENTURA BLVD #40 TARZANA, CA 91356 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/24/2021 | Approved | MARK FERRARI |
| Deputy Drilled-In Anchors | 10/12/2021 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 10/13/2021 | Partial Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 10/14/2021 | Conditional Approval | BRUCE CAMPBELL |
| Wood Frame | 2/9/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 3/23/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 4/28/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 5/2/2022 | Corrections Issued | DARRYL ARNOLD |
| Final | 8/9/2022 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/9/2022 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 8/9/2022 | Approved | DARRYL ARNOLD |