804-806 1/2 E 87TH PL 90002
Certificate Information: 804-806 1/2 E 87TH PL 90002
- Application / Permit
- 20016-10000-31698
- Plan Check / Job No.
- B20LA22732
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT (E) GARAGE TO AN ADU
- Permit Issued
- Issued on 10/5/2021
- Issuing Office
- Current Status
- CofO Issued on 9/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2020 | RICARDO RAMIREZ |
| Corrections Issued | 12/19/2020 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 9/10/2021 | FERNANDO FLORES |
| Plan Check Approved | 10/4/2021 | FERNANDO FLORES |
| Issued | 10/5/2021 | APPLICANT |
| Building Plans Picked Up | 10/15/2021 | APPLICANT |
| CofO in Progress | 9/2/2025 | SCOTT FINNILA |
| CofO Issued | 9/5/2025 | DEROLD HAUFF |
| Permit Finaled | 9/5/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 1/25/2021 | CECILIO NAVARRO |
| Tenant Habitability Plan | Cleared | 8/30/2021 | ISMAEL HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2021 | CECILIO NAVARRO |
Contact Information
| Contractor | Vickers Construction Company Inc; Lic. No.: 1008338-B | 952 E 116TH STREET LOS ANGELES, CA 90059 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/22/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 3/21/2023 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 3/21/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 3/21/2023 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/23/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 3/23/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 3/23/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/23/2023 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 3/23/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/29/2023 | Conditional Approval | LILIANA PORTILLO |
| Insulation | 3/29/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2023 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 4/10/2023 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 6/5/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Final | 6/5/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 6/5/2023 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 6/5/2023 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 6/12/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 6/12/2023 | Approved | STUART CHAPMAN |
| Final | 6/12/2023 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 6/12/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 6/12/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 6/12/2023 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 6/12/2023 | Approved | STUART CHAPMAN |
| Final | 9/2/2025 | OK to Issue CofO | SCOTT FINNILA |