1307 S BARRY AVE 90025
Certificate Information: 1307 S BARRY AVE 90025
- Application / Permit
- 20016-10000-31650
- Plan Check / Job No.
- B20LA22708
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: Soft-Story seismic retrofit per LABC Chapter 93: Install one Moment Frame and One Cantilever column
- Permit Issued
- Issued on 11/5/2021
- Issuing Office
- Metro
- Current Status
- CofC Issued on 2/24/2022
Permit Application Status History
| Submitted | 12/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2020 | JESSE VIDUYA |
| Corrections Issued | 12/30/2020 | JESSE VIDUYA |
| Quality Review Completed | 1/4/2021 | HANS SANTIAGO |
| Plan Check Approved | 1/19/2021 | JESSE VIDUYA |
| Issued | 11/5/2021 | APPLICANT |
| Building Plans Picked Up | 11/8/2021 | APPLICANT |
| OK for CofC | 2/23/2022 | GRANT WOODS |
| CofC Issued | 2/24/2022 | DAVID TSAU |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/12/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Midwest Construction; Lic. No.: 955704-B | 4220 WEST 64TH STREET INGLEWOOD, CA 90302 |
| Engineer | Puliyadi,, Senthilnath Surendran; Lic. No.: C71630 | 22320 FOOTHILL BLVD STE 600 HAYWARD, CA 94541 |
| Engineer | Puliyadi,, Senthilnath Surendran; Lic. No.: NA71630 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/18/2021 | Approved | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 12/7/2021 | Not Ready for Inspection | ALAN NOVAK |
| Footing/Foundation/Slab | 12/7/2021 | Not Ready for Inspection | ALAN NOVAK |
| Wood Frame | 2/1/2022 | Partial Approval | JOHN DODGE |
| Interior/Exterior Lathing | 2/7/2022 | Not Ready for Inspection | ALAN NOVAK |
| Insulation | 2/8/2022 | Approved | JOHN DODGE |
| Wood Frame | 2/8/2022 | Partial Approval | JOHN DODGE |
| Interior/Exterior Lathing | 2/10/2022 | Approved | JOHN DODGE |
| Wood Frame | 2/10/2022 | Approved | JOHN DODGE |
| Final | 2/17/2022 | Not Ready for Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 2/17/2022 | SGSOV Not Ready | GRANT WOODS |
| Smoke Detectors | 2/17/2022 | Approved | GRANT WOODS |
| Final | 2/23/2022 | OK for CofC | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 2/23/2022 | SGSOV Approved | GRANT WOODS |