900-902 S ELLERY DR 90732

Certificate Information: 900-902 S ELLERY DR 90732

Application / Permit
20016-10000-31614
Plan Check / Job No.
B20LA22680
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan - SFD REMODEL AND CONVERT BASEMENT USED AS NANNY QUARTERS/RERROOM INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(B)(5)
Permit Issued
Issued on 4/15/2021
Issuing Office
Current Status
CofO Issued on 6/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 LARRY LEE
Corrections Issued 12/10/2020 LARRY LEE
Applicant returned to address corrections 2/3/2021 MONICA RAMIREZ
Applicant returned to address corrections 3/4/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 3/15/2021 LARRY LEE
Plan Check Approved 3/23/2021 LARRY LEE
Issued 4/15/2021 APPLICANT
CofO in Progress 5/31/2024 PAUL REECE
Permit Finaled 6/4/2024 PAUL BECKER
CofO Issued 6/4/2024 PAUL BECKER
Permit Finaled 6/4/2024 PAUL BECKER

Permit Application Clearance Information

Address approval Cleared 12/31/2020 ERIK BEASLEY
Sewer availability Cleared 12/31/2020 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 1/11/2021 ERIK BEASLEY
ZA Case Cleared 1/13/2021 SARAHI ORTEGA
ZA Case Cleared 1/13/2021 SARAHI ORTEGA

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Paul Yonggyun; Lic. No.: C87401 800 S VICTORIA AVE L#1720      VENTURA, CA 93009

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 5/3/2021 Corrections Issued ANDREW BEELI
ELECTRICAL-Rough 5/3/2021 Not Ready for Inspection ANDREW BEELI
Footing/Foundation/Slab 5/10/2021 Not Ready for Inspection ANDREW BEELI
ELECTRICAL-Rough 5/13/2021 Approved ANDREW BEELI
ELECTRICAL-Rough 5/19/2021 Approved ANDREW BEELI
Insulation 5/19/2021 Partial Approval ANDREW BEELI
Drywall Nailing 5/25/2021 Approved ANDREW BEELI
Insulation 5/25/2021 Approved ANDREW BEELI
Final 10/28/2021 Corrections Issued ANDREW BEELI
BUILDING-Rough-Frame 11/1/2021 Approved ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 11/1/2021 SGSOV Not Ready ANDREW BEELI
Smoke Detectors 11/1/2021 Approved ANDREW BEELI
Final 2/28/2022 Corrections Issued ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 2/28/2022 SGSOV Not Ready ANDREW BEELI
Final 9/6/2022 Conditional Approval ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 9/6/2022 SGSOV Approved ANDREW BEELI
Final 5/31/2024 OK to Issue CofO PAUL REECE