900-902 S ELLERY DR 90732
Certificate Information: 900-902 S ELLERY DR 90732
- Application / Permit
- 20016-10000-31614
- Plan Check / Job No.
- B20LA22680
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan - SFD REMODEL AND CONVERT BASEMENT USED AS NANNY QUARTERS/RERROOM INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(B)(5)
- Permit Issued
- Issued on 4/15/2021
- Issuing Office
- Current Status
- CofO Issued on 6/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | LARRY LEE |
| Corrections Issued | 12/10/2020 | LARRY LEE |
| Applicant returned to address corrections | 2/3/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 3/4/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 3/15/2021 | LARRY LEE |
| Plan Check Approved | 3/23/2021 | LARRY LEE |
| Issued | 4/15/2021 | APPLICANT |
| CofO in Progress | 5/31/2024 | PAUL REECE |
| Permit Finaled | 6/4/2024 | PAUL BECKER |
| CofO Issued | 6/4/2024 | PAUL BECKER |
| Permit Finaled | 6/4/2024 | PAUL BECKER |
Permit Application Clearance Information
| Address approval | Cleared | 12/31/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 12/31/2020 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2021 | ERIK BEASLEY |
| ZA Case | Cleared | 1/13/2021 | SARAHI ORTEGA |
| ZA Case | Cleared | 1/13/2021 | SARAHI ORTEGA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Paul Yonggyun; Lic. No.: C87401 | 800 S VICTORIA AVE L#1720 VENTURA, CA 93009 |
Inspector Information
| KELLY WARNER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BECKER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| KEITH EDGHILL, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GONZALEZ, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/3/2021 | Corrections Issued | ANDREW BEELI |
| ELECTRICAL-Rough | 5/3/2021 | Not Ready for Inspection | ANDREW BEELI |
| Footing/Foundation/Slab | 5/10/2021 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Rough | 5/13/2021 | Approved | ANDREW BEELI |
| ELECTRICAL-Rough | 5/19/2021 | Approved | ANDREW BEELI |
| Insulation | 5/19/2021 | Partial Approval | ANDREW BEELI |
| Drywall Nailing | 5/25/2021 | Approved | ANDREW BEELI |
| Insulation | 5/25/2021 | Approved | ANDREW BEELI |
| Final | 10/28/2021 | Corrections Issued | ANDREW BEELI |
| BUILDING-Rough-Frame | 11/1/2021 | Approved | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 11/1/2021 | SGSOV Not Ready | ANDREW BEELI |
| Smoke Detectors | 11/1/2021 | Approved | ANDREW BEELI |
| Final | 2/28/2022 | Corrections Issued | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 2/28/2022 | SGSOV Not Ready | ANDREW BEELI |
| Final | 9/6/2022 | Conditional Approval | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 9/6/2022 | SGSOV Approved | ANDREW BEELI |
| Final | 5/31/2024 | OK to Issue CofO | PAUL REECE |