2303 S SPAULDING AVE 90016

Certificate Information: 2303 S SPAULDING AVE 90016

Application / Permit
20016-10000-31610
Plan Check / Job No.
B20LA22677
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ADU PER GCS 65852.2 and 65852.22
Permit Issued
Issued on 4/14/2021
Issuing Office
Current Status
CofO Issued on 9/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2020 APPLICANT
Assigned to Plan Check Engineer 12/11/2020 LARRY LEE
Corrections Issued 12/11/2020 LARRY LEE
Applicant returned to address corrections 12/31/2020 HERNAN ARREOLA
Applicant returned to address corrections 2/18/2021 CRYSTEL MAALOUF
Plan Check Approved 2/24/2021 CRYSTEL MAALOUF
Issued 4/14/2021 APPLICANT
CofO in Progress 8/21/2023 JOSE AVILA
Permit Finaled 9/25/2023 DEROLD HAUFF
CofO Issued 9/25/2023 DEROLD HAUFF
Permit Finaled 9/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/17/2020 RENZ SORIANO
Sewer availability Cleared 12/17/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 12/21/2020 RENZ SORIANO
Construction within easement Cleared 2/16/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Chen,, Junfei; Lic. No.: NA85841       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/31/2022 Approved JOSE AVILA
Pre-Inspection 2/7/2023 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 2/17/2023 Partial Approval JOSE AVILA
PLUMBING-Rough 3/7/2023 Partial Approval JOSE AVILA
Excavation/Setback/Form/Re-Bar 3/14/2023 Approved JOSE AVILA
Footing/Foundation/Slab 3/14/2023 Approved JOSE AVILA
ELECTRICAL-Rough 4/5/2023 Corrections Issued JOSE AVILA
PLUMBING-Rough 4/5/2023 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Rough 4/11/2023 Approved JOSE AVILA
HVAC-Rough 4/11/2023 Approved JOSE AVILA
PLUMBING-Rough 4/11/2023 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 4/18/2023 Approved JOSE AVILA
Green Building Rough 4/18/2023 Approved JOSE AVILA
MERV13>=Rough 4/18/2023 Approved JOSE AVILA
Insulation 4/26/2023 Approved JOSE AVILA
Interior/Exterior Lathing 4/26/2023 Approved JOSE AVILA
Shower Pan 4/26/2023 Approved JOSE AVILA
Drywall Nailing 5/2/2023 Approved LILIANA PORTILLO
Final 7/5/2023 No Access for Inspection JOSE AVILA
Final 7/17/2023 Partial Inspection JOSE AVILA
Service/Power Release 7/21/2023 Corrections Issued JOSE AVILA
Final 7/31/2023 Corrections Issued JOSE AVILA
MERV13>=Final 7/31/2023 Not Ready for Inspection JOSE AVILA
SGSOV-Seismic Gas S/O Valve 7/31/2023 SGSOV Approved JOSE AVILA
Smoke Detectors 7/31/2023 Approved JOSE AVILA
Final 8/17/2023 OK to Issue CofO JOSE AVILA
MERV13>=Final 8/17/2023 Approved JOSE AVILA
Service/Power Release 8/17/2023 Approved JOSE AVILA