7537 W VALAHO DR 91042

Certificate Information: 7537 W VALAHO DR 91042

Application / Permit
20016-10000-31598
Plan Check / Job No.
B20LA22668
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERTING EXT'G GARAGE AND STORAGE TO DETACHED ADU PER STATE LAW (1-STORY)
Permit Issued
Issued on 7/21/2021
Issuing Office
Current Status
CofO Issued on 1/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2020 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 CARLOS MONTES
Corrections Issued 1/20/2021 CARLOS MONTES
Quality Review Completed 2/2/2021 TU HUA
Applicant returned to address corrections 4/27/2021 CARLOS MONTES
Applicant returned to address corrections 5/27/2021 CARLOS MONTES
Applicant returned to address corrections 6/24/2021 CARLOS MONTES
Applicant returned to address corrections 7/7/2021 CARLOS MONTES
Plan Check Approved 7/15/2021 CARLOS MONTES
Issued 7/21/2021 APPLICANT
CofO in Progress 12/13/2022 DAVID ANDERSON
Permit Finaled 1/14/2023 MICHAEL SMITH
CofO Issued 1/14/2023 MICHAEL SMITH
Permit Finaled 1/14/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/23/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/23/2021 ADRIAN CASTRO
Sewer availability Cleared 4/23/2021 ADRIAN CASTRO
Grading Pre-Inspection Cleared 5/20/2021 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/10/2022 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 3/10/2022 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 3/15/2022 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 6/22/2022 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Not Ready for Inspection DAVID ANDERSON
Wood Frame 6/27/2022 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Approved DAVID ANDERSON
Insulation 6/28/2022 Approved DAVID ANDERSON
BUILDING-Rough-Frame 10/3/2022 Approved DAVID ANDERSON
ELECTRICAL-Final 10/3/2022 Corrections Issued DAVID ANDERSON
Final 10/3/2022 Corrections Issued DAVID ANDERSON
Gas Test 10/3/2022 Not Ready for Inspection DAVID ANDERSON
Green Building Final 10/3/2022 Approved DAVID ANDERSON
Green Building Rough 10/3/2022 Approved DAVID ANDERSON
PLUMBING-Final 10/3/2022 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 10/3/2022 SGSOV Not Ready DAVID ANDERSON
Smoke Detectors 10/3/2022 Approved DAVID ANDERSON
ELECTRICAL-Final 12/2/2022 Approved MATTHEW NELSON
Final 12/2/2022 Corrections Issued MATTHEW NELSON
PLUMBING-Final 12/2/2022 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 12/2/2022 SGSOV Approved MATTHEW NELSON
ELECTRICAL-Final 12/9/2022 Approved DAVID ANDERSON
Final 12/9/2022 Corrections Issued DAVID ANDERSON
PLUMBING-Final 12/9/2022 Approved DAVID ANDERSON
Final 12/13/2022 OK to Issue CofO DAVID ANDERSON