7516 S LA SALLE AVE 90047
Certificate Information: 7516 S LA SALLE AVE 90047
- Application / Permit
- 20016-10000-31512
- Plan Check / Job No.
- B20LA22614
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 18'-2" X 20'-4" (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
- Permit Issued
- Issued on 3/30/2021
- Issuing Office
- Current Status
- CofO Issued on 6/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2020 | RACHEL BEYENE |
| Corrections Issued | 12/23/2020 | RACHEL BEYENE |
| Applicant returned to address corrections | 1/15/2021 | RARES BODEA |
| Issued | 3/30/2021 | APPLICANT |
| Building Plans Picked Up | 5/3/2021 | APPLICANT |
| CofO in Progress | 6/15/2023 | ENRIQUE MIRELES |
| CofO in Progress | 6/15/2023 | ENRIQUE MIRELES |
| Permit Finaled | 6/29/2023 | DEROLD HAUFF |
| CofO Issued | 6/29/2023 | DEROLD HAUFF |
| Permit Finaled | 6/29/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 1/7/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2021 | CECILIO NAVARRO |
| Construction near power lines | Cleared | 3/17/2021 | RIDWAN HARDY |
Contact Information
| No Data Available. |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/23/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 9/20/2022 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 9/20/2022 | Not Ready for Inspection | SABAS ALONSO |
| Sewer | 9/20/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 9/20/2022 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 10/19/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 10/19/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/19/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/28/2022 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 11/7/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 1/24/2023 | Approved | ENRIQUE MIRELES |
| Final | 1/24/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 1/24/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 1/24/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 1/24/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 1/24/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 1/24/2023 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 1/24/2023 | Approved | ENRIQUE MIRELES |
| Final | 2/7/2023 | Corrections Issued | ENRIQUE MIRELES |