6110 E MYOSOTIS ST 90042

Certificate Information: 6110 E MYOSOTIS ST 90042

Application / Permit
20016-10000-31411
Plan Check / Job No.
B20LA22517
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING TWO CAR GARAGE INTO ADU PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 5/19/2021
Issuing Office
Current Status
CofO Issued on 1/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/7/2020 APPLICANT
Assigned to Plan Check Engineer 12/16/2020 RAHEL BEYENE
Corrections Issued 12/23/2020 RAHEL BEYENE
Applicant returned to address corrections 1/12/2021 JESSE JIMENEZ
Applicant returned to address corrections 2/23/2021 RICARDO RAMIREZ
Applicant returned to address corrections 4/24/2021 TSE MING HUANG
Plan Check Approved 5/13/2021 LUKE GONZALES
Issued 5/19/2021 APPLICANT
Building Plans Picked Up 5/21/2021 APPLICANT
CofO in Progress 1/7/2022 CRAIG VAUGHAN
Permit Finaled 1/13/2022 DEROLD HAUFF
Permit Finaled 1/13/2022 DEROLD HAUFF
CofO Issued 1/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/22/2021 CELINA MORENO
Sewer availability Cleared 1/22/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/25/2021 CELINA MORENO
Hydrant and Access approval Cleared 4/15/2021 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/9/2021 Partial Inspection COREY HUPP
BUILDING-Rough-Frame 6/29/2021 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 6/29/2021 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 6/29/2021 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 7/8/2021 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 7/8/2021 Corrections Issued COREY HUPP
Footing/Foundation/Slab 7/28/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 7/28/2021 Partial Approval CRAIG VAUGHAN
Underground Mechanical 7/28/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 8/5/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 8/5/2021 Approved CRAIG VAUGHAN
Insulation 8/5/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 8/5/2021 Approved CRAIG VAUGHAN
Drywall Nailing 8/12/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 9/1/2021 Approved CRAIG VAUGHAN
Service/Power Release 11/2/2021 Not Ready for Inspection OSVALDO PARAMO
Final 11/8/2021 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 11/8/2021 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 11/8/2021 Corrections Issued HAMIK HARTOUNIAN
Final 11/15/2021 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 11/15/2021 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 11/15/2021 Approved CRAIG VAUGHAN
Final 12/8/2021 Corrections Issued CRAIG VAUGHAN
Final 12/22/2021 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Final 1/6/2022 Approved CRAIG VAUGHAN
Final 1/6/2022 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 1/6/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 1/6/2022 Approved CRAIG VAUGHAN