2353 S PORTLAND ST 90007
Certificate Information: 2353 S PORTLAND ST 90007
- Application / Permit
- 20016-10000-31410
- Plan Check / Job No.
- B20LA22515
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Conversion of entire (E) garages at the first floor in an (E) apartment into (10) ADUs per state law GCS 65852.2(e)(1)(C).
- Permit Issued
- Issued on 12/9/2021
- Issuing Office
- Current Status
- CofO Issued on 1/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | HELEN NGUYEN |
| Corrections Issued | 1/11/2021 | HELEN NGUYEN |
| Quality Review Completed | 1/13/2021 | GARO TELMI |
| Applicant returned to address corrections | 5/20/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 5/25/2021 | HELEN NGUYEN |
| Green Plans Picked Up | 8/5/2021 | APPLICANT |
| Applicant returned to address corrections | 9/17/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 10/14/2021 | HELEN NGUYEN |
| Disabled Access Plans Picked Up | 10/14/2021 | APPLICANT |
| Applicant returned to address corrections | 11/10/2021 | HELEN NGUYEN |
| Plan Check Approved | 12/9/2021 | HELEN NGUYEN |
| Issued | 12/9/2021 | APPLICANT |
| Building Plans Picked Up | 12/10/2021 | APPLICANT |
| TCO Issued (Expire Date: 04-26-2023) | 10/28/2022 | TED RIES |
| CofO in Progress | 1/17/2023 | ERNESTO CORRAL |
| Permit Finaled | 1/17/2023 | ERNESTO CORRAL |
| CofO Issued | 1/17/2023 | ERNESTO CORRAL |
| Permit Finaled | 1/17/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| "Q" conditions | Cleared | 2/3/2021 | DANIEL CORONADO |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2021 | CECILIO NAVARRO |
| ZI | Cleared | 2/3/2021 | DANIEL CORONADO |
| Address approval | Cleared | 2/5/2021 | CECILIO NAVARRO |
| Tenant Habitability Plan | Cleared | 2/11/2021 | MICHAEL SOTO |
| Miscellaneous | Cleared | 3/15/2021 | HELEN NGUYEN |
| Fire Marshal Fire Life Safety | Cleared | 3/26/2021 | WILLIAM JOHNS |
| HPOZ | Cleared | 3/26/2021 | KATIE DEBIASE |
| Sewer availability | Cleared | 5/14/2021 | CECILIO NAVARRO |
| Green Code | Cleared | 8/3/2021 | AARON COSTA |
| DAS Clearance | Cleared | 11/17/2021 | HELEN NGUYEN |
Contact Information
| Architect | Badie,, Amin; Lic. No.: C28846 | 4386 BECK AVENUE STUDIO CITY, CA 91604 |
| Contractor | Dh Remodel Services; Lic. No.: 1030925-B | 5850 W 3RD STREET #160 LOS ANGELES, CA 90036 |
| Engineer | Arriola,, Kirby Norman; Lic. No.: C31416 | PO BOX 5566 OXNARD, CA 93031 |
| Geologist | Fujita,, Samantha Jane; Lic. No.: GEO9042 | 16414 VAN NESS AVE TORRANCE, CA 90504 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Rough | 3/15/2022 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Pre-Inspection | 3/15/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 3/21/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Pre-Inspection | 3/21/2022 | Approved | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 3/25/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Pre-Inspection | 3/25/2022 | Approved | RUSSELL BONVOULOIR |
| Green Building Rough | 3/30/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| METHANE-Rough | 3/30/2022 | Approved | RUSSELL BONVOULOIR |
| Pre-Inspection | 3/30/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Wood Frame | 3/30/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Green Building Rough | 4/18/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Insulation | 4/18/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Pre-Inspection | 4/18/2022 | Approved | RUSSELL BONVOULOIR |
| Wood Frame | 4/18/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Insulation | 4/19/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Light Gage Steel Frame | 4/19/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Pre-Inspection | 4/19/2022 | Approved | RUSSELL BONVOULOIR |
| Interior/Exterior Lathing | 4/22/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Pre-Inspection | 4/22/2022 | Approved | RUSSELL BONVOULOIR |
| Interior/Exterior Lathing | 4/25/2022 | Approved | TIMOTHY BUXTON |
| Pre-Inspection | 4/25/2022 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 4/28/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Insulation | 4/28/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Interior/Exterior Lathing | 4/28/2022 | Approved | RUSSELL BONVOULOIR |
| Pre-Inspection | 4/28/2022 | Approved | RUSSELL BONVOULOIR |
| Drywall Nailing | 4/29/2022 | Approved | TIMOTHY BUXTON |
| Insulation | 4/29/2022 | Approved | TIMOTHY BUXTON |
| Pre-Inspection | 4/29/2022 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 5/3/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Pre-Inspection | 5/3/2022 | Approved | RUSSELL BONVOULOIR |
| Drywall Nailing | 5/9/2022 | Corrections Issued | RUSSELL BONVOULOIR |
| Wall Anchors | 5/9/2022 | Approved | RUSSELL BONVOULOIR |
| Drywall Nailing | 5/18/2022 | Approved | RUSSELL BONVOULOIR |
| Pre-Inspection | 6/16/2022 | Approved | RAFAEL ESPINOZA |
| Final | 8/15/2022 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Green Building Final | 8/15/2022 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Green Building Rough | 8/15/2022 | Approved | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 8/15/2022 | SGSOV Not Ready | RUSSELL BONVOULOIR |
| Smoke Detectors | 8/15/2022 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Wood Frame | 8/15/2022 | Approved | RUSSELL BONVOULOIR |
| Final | 11/2/2022 | Corrections Issued | RUSSELL BONVOULOIR |
| Green Building Final | 11/2/2022 | Approved | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 11/2/2022 | SGSOV Approved | RUSSELL BONVOULOIR |
| Smoke Detectors | 11/2/2022 | Approved | RUSSELL BONVOULOIR |
| Final | 11/9/2022 | Not Ready for Inspection | JAMES POWERS |
| Final | 11/15/2022 | Conditional Approval | RUSSELL BONVOULOIR |