1375 E 15TH ST 90021
Certificate Information: 1375 E 15TH ST 90021
- Application / Permit
- 20016-10000-31272
- Plan Check / Job No.
- B20LA22286
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (12) Manufacturing
- Work Description
- CHANGE OF USE FROM (E) WAREHOUSE & OFFICE TO (N) BREWERY & OFFICE
- Permit Issued
- Issued on 9/30/2021
- Issuing Office
- Current Status
- CofO Issued on 11/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2020 | LAMAR DAVIS |
| Corrections Issued | 12/22/2020 | LAMAR DAVIS |
| Quality Review Completed | 1/13/2021 | GARO TELMI |
| Disabled Access Plans Picked Up | 1/19/2021 | APPLICANT |
| Green Plans Picked Up | 1/19/2021 | APPLICANT |
| Applicant returned to address corrections | 9/9/2021 | LAMAR DAVIS |
| Plan Check Approved | 9/24/2021 | LAMAR DAVIS |
| Issued | 9/30/2021 | APPLICANT |
| CofO in Progress | 11/3/2023 | KATY RAMIREZ |
| Permit Finaled | 11/6/2023 | ERNESTO CORRAL |
| CofO Issued | 11/6/2023 | ERNESTO CORRAL |
| Permit Finaled | 11/6/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| "D" conditions | Cleared | 4/28/2021 | JOE LUCKEY |
| Historic Resource Verification | Cleared | 5/19/2021 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 5/19/2021 | DAVID URITA |
| Green Code | Cleared | 5/20/2021 | AARON COSTA |
| DAS Clearance | Cleared | 6/10/2021 | SHINE LIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2021 | THOMAS LANG |
| Sewer availability | Cleared | 7/2/2021 | THOMAS LANG |
Contact Information
| Architect | Ryan,, Oonagh C; Lic. No.: C33156 | 923 E 3RD STREET #105 LOS ANGELES, CA 90013 |
| Contractor | E C F Construction; Lic. No.: 528529-B | 311 EN CANADA DRIVE LA HABRA HEIGHTS, CA 90631 |
| Engineer | Tan,, Charles; Lic. No.: S4758 | 3161 DRIGGS AVENUE ROSEMEAD, CA 91770 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/13/2021 | Conditional Approval | DANIEL COLLINS |
| Wood Frame | 10/26/2021 | Partial Approval | TIMOTHY BUXTON |
| Deputy Drilled-In Anchors | 12/8/2021 | Conditional Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 12/15/2021 | Partial Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 1/3/2022 | Conditional Approval | ERNESTO CORRAL |
| Footing/Foundation/Slab | 1/4/2022 | Approved | TIMOTHY BUXTON |
| Deputy Reinf. Concrete | 1/6/2022 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Reinf. Concrete | 1/13/2022 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Drilled-In Anchors | 1/19/2022 | Conditional Approval | TIMOTHY BUXTON |
| Wood Frame | 2/17/2022 | Conditional Approval | BRUCE CAMPBELL |
| Light Gage Steel Frame | 4/26/2022 | Partial Approval | TED RIES |
| Insulation | 5/6/2022 | Approved | KATY RAMIREZ |
| Drywall Nailing | 5/11/2022 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 6/14/2022 | Not Ready for Inspection | TIMOTHY BUXTON |
| T-Bar Ceiling | 10/11/2022 | Partial Approval | MARK FERRARI |
| T-Bar Ceiling | 12/12/2022 | Partial Approval | RONALD JIMENEZ |
| Special/Order Compliance | 2/1/2023 | Off-Hour Fees Due | |
| Final | 7/20/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Green Building Final | 7/20/2023 | Not Ready for Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 7/20/2023 | SGSOV Not Ready | KATY RAMIREZ |
| Smoke Detectors | 7/20/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 8/21/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Green Building Final | 8/21/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 8/21/2023 | SGSOV Not Ready | MARTIN TAVITIAN |
| Smoke Detectors | 8/21/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Final | 8/24/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Final | 8/24/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/24/2023 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 8/24/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 9/14/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Green Building Final | 9/14/2023 | Approved | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 9/14/2023 | SGSOV Not Ready | KATY RAMIREZ |
| Smoke Detectors | 9/14/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 10/23/2023 | Partial Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 10/23/2023 | SGSOV Approved | KATY RAMIREZ |
| Smoke Detectors | 10/23/2023 | Approved | KATY RAMIREZ |
| Final | 11/1/2023 | OK to Issue CofO | KATY RAMIREZ |