1672 1/2 E 112TH ST 90059

Certificate Information: 1672 1/2 E 112TH ST 90059

Application / Permit
20016-10000-31256
Plan Check / Job No.
B20LA22271
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE (380sqft) TO AN ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 6/10/2021
Issuing Office
Current Status
CofO Issued on 3/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2020 APPLICANT
Assigned to Plan Check Engineer 12/15/2020 STANLEY RAAP
Corrections Issued 12/21/2020 STANLEY RAAP
Plan Check Approved 4/23/2021 STANLEY RAAP
Issued 6/10/2021 APPLICANT
Building Plans Picked Up 7/6/2021 APPLICANT
CofO in Progress 3/21/2022 EUGENE CASSIDY
Permit Finaled 3/22/2022 DEROLD HAUFF
CofO Issued 3/22/2022 DEROLD HAUFF
Permit Finaled 3/22/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/3/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 2/4/2021 THOMAS LANG
Hydrant and Access approval Cleared 3/9/2021 MATTHEW CRAIG
Sewer availability Cleared 5/5/2021 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/10/2021 Partial Approval EUGENE CASSIDY
Deputy Methane Barrier 8/17/2021 Conditional Approval WILLIAM ROSE
Footing/Foundation/Slab 8/18/2021 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 8/23/2021 Approved EUGENE CASSIDY
Footing/Foundation/Slab 8/23/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 9/22/2021 Corrections Issued EUGENE CASSIDY
PLUMBING-Final 9/22/2021 Corrections Issued EUGENE CASSIDY
Wood Frame 9/22/2021 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 10/4/2021 Partial Approval EUGENE CASSIDY
ELECTRICAL-Final 10/4/2021 Partial Approval EUGENE CASSIDY
Green Building Rough 10/4/2021 Approved EUGENE CASSIDY
PLUMBING-Final 10/4/2021 Corrections Issued EUGENE CASSIDY
HVAC-Rough 10/12/2021 Partial Approval EUGENE CASSIDY
Insulation 10/12/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/12/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 10/12/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 10/15/2021 Approved EUGENE CASSIDY
PLUMBING-Final 10/15/2021 Approved EUGENE CASSIDY
Drywall Nailing 10/22/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/22/2021 Approved EUGENE CASSIDY
Final 11/23/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 11/23/2021 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 11/23/2021 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 11/23/2021 Corrections Issued EUGENE CASSIDY
Final 12/1/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 12/1/2021 Approved EUGENE CASSIDY
Smoke Detectors 12/1/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 12/16/2021 Approved EUGENE CASSIDY
Final 12/16/2021 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 12/16/2021 Approved EUGENE CASSIDY
Final 3/18/2022 OK to Issue CofO EUGENE CASSIDY