7954 N LINDLEY AVE 91335
Certificate Information: 7954 N LINDLEY AVE 91335
- Application / Permit
- 20016-10000-31255
- Plan Check / Job No.
- B20LA22270
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT EXISTING REC ROOM AND STORAGE (PERMIT NUMBER: 15014-20000-03014) TO NEW ACCESSORY DWELLINT UNIT PER (Ord. 186,481) and Los Angeles Municipal Code (LAMC) Section 12.22A.33. (c) &(d). (CARPORT AND STORAGE TO REMAIN)
- Permit Issued
- Issued on 10/29/2024
- Issuing Office
- Current Status
- CofO Issued on 2/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2021 | SELLA BENYAMIN |
| Corrections Issued | 4/15/2021 | ZAW HAN |
| Plan Check Approved | 11/20/2021 | SELLA BENYAMIN |
| Plan Check Approved | 10/12/2023 | JEROME MAGAT PALMA |
| Issued | 10/29/2024 | APPLICANT |
| CofO in Progress | 3/27/2025 | ARUTYUN MADATYAN |
| No Progress | 4/3/2025 | ROBERT GOLD |
| CofO in Progress | 4/3/2025 | ROBERT GOLD |
| CofO in Progress | 4/3/2025 | ROBERT GOLD |
| Permit Finaled | 2/21/2026 | MICHAEL PELHAM |
| CofO Issued | 2/21/2026 | MICHAEL PELHAM |
| Permit Finaled | 2/21/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 5/10/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/10/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 5/10/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/10/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Final | 11/4/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 11/4/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 11/4/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Insulation | 11/4/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Sewer | 11/4/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 11/4/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 11/19/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Gas Test | 11/19/2024 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 11/19/2024 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 12/13/2024 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 12/13/2024 | Approved | ARUTYUN MADATYAN |
| Rough-Elec/Plmb/HVAC | 12/13/2024 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 3/6/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 3/6/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 3/6/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 3/6/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 3/6/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Drywall Nailing | 3/19/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 3/19/2025 | Approved | ARUTYUN MADATYAN |
| Final | 3/19/2025 | Corrections Issued | ARUTYUN MADATYAN |
| HVAC-Final | 3/19/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 3/19/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 3/19/2025 | Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 3/19/2025 | Approved | ARUTYUN MADATYAN |
| Final | 3/26/2025 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Final | 3/26/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 3/26/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Final | 4/4/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Special/Order Compliance | 8/8/2025 | Partial Inspection | ARUTYUN MADATYAN |
| Special/Order Compliance | 11/10/2025 | Corrections Issued | JUAN ALVARADO |