1341 1/2 W 218TH ST 90501

Certificate Information: 1341 1/2 W 218TH ST 90501

Application / Permit
20016-10000-31253
Plan Check / Job No.
B20LA22265
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED A.D.U. AT REAR OF LOT.
Permit Issued
Issued on 11/24/2021
Issuing Office
Current Status
CofO Issued on 9/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2020 APPLICANT
Assigned to Plan Check Engineer 1/7/2021 JOE VO
Corrections Issued 1/13/2021 JOE VO
Quality Review Completed 1/29/2021 MINYE PAK
Applicant returned to address corrections 7/7/2021 JOE VO
Plan Check Approved 11/5/2021 JOE VO
Issued 11/24/2021 APPLICANT
CofO in Progress 7/6/2023 EUGENE CASSIDY
Permit Finaled 9/29/2023 ANSON MAGLASANG
CofO Issued 9/29/2023 ANSON MAGLASANG
Permit Finaled 9/29/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 2/17/2021 ERIK BEASLEY
Permit Cleared 3/3/2021 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 3/4/2021 ERIK BEASLEY
Roof/Waste drainage to street Cleared 3/4/2021 ERIK BEASLEY
Sewer availability Cleared 3/12/2021 ERIK BEASLEY
Hydrant and Access approval Cleared 5/18/2021 KURT CORRAL
Low Impact Development Cleared 10/28/2021 KHAING AYE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/9/2021 Not Ready for Inspection JOHN KLARIN
Pre-Inspection 12/9/2021 Approved JOHN KLARIN
Deputy Drilled-In Anchors 12/10/2021 Approved JOHN KLARIN
Footing/Foundation/Slab 12/20/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 12/27/2021 Not Ready for Inspection JOHN KLARIN
Excavation/Setback/Form/Re-Bar 12/27/2021 Approved JOHN KLARIN
Green Building Rough 12/27/2021 Not Ready for Inspection JOHN KLARIN
Verify Sprinkler Sign Off 12/27/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 2/9/2022 Corrections Issued EUGENE CASSIDY
Green Building Rough 2/9/2022 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 2/9/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 3/16/2022 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 3/16/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 4/12/2022 Approved EUGENE CASSIDY
HVAC-Rough 4/12/2022 Corrections Issued EUGENE CASSIDY
Insulation 4/12/2022 Partial Approval EUGENE CASSIDY
Wood Frame 4/12/2022 Partial Approval EUGENE CASSIDY
HVAC-Final 4/15/2022 Approved JOHN KLARIN
HVAC-Rough 4/15/2022 Approved JOHN KLARIN
Insulation 4/15/2022 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 4/19/2022 Approved JOHN KLARIN
Gas Test 4/19/2022 Approved JOHN KLARIN
Insulation 4/19/2022 Approved JOHN KLARIN
PLUMBING-Rough 4/19/2022 Approved JOHN KLARIN
Drywall Nailing 4/22/2022 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 4/22/2022 Approved EUGENE CASSIDY
Drywall Nailing 4/27/2022 Approved EUGENE CASSIDY
Interior/Exterior Lathing 4/27/2022 Approved EUGENE CASSIDY
Sewer 4/27/2022 Approved EUGENE CASSIDY
Interior/Exterior Lathing 4/29/2022 Approved EUGENE CASSIDY
Sewer 4/29/2022 Approved EUGENE CASSIDY
Shower Pan 4/29/2022 Approved EUGENE CASSIDY
Shower Pan 5/2/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 5/23/2022 Corrections Issued EUGENE CASSIDY
PLUMBING-Final 5/23/2022 Corrections Issued EUGENE CASSIDY
Smoke Detectors 5/23/2022 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 7/18/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 7/18/2022 Not Ready for Inspection EUGENE CASSIDY
Final 7/18/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 7/18/2022 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/18/2022 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 7/18/2022 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 7/18/2022 Approved EUGENE CASSIDY
Final 9/16/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 9/16/2022 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/16/2022 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 9/16/2022 Not Ready for Inspection EUGENE CASSIDY
Final 2/22/2023 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/22/2023 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 2/22/2023 Not Required EUGENE CASSIDY
ELECTRICAL-Final 6/29/2023 Approved EUGENE CASSIDY
Final 6/29/2023 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/29/2023 SGSOV Approved EUGENE CASSIDY
Final 7/5/2023 OK to Issue CofO EUGENE CASSIDY
PLUMBING-Final 7/5/2023 Approved EUGENE CASSIDY