1341 1/2 W 218TH ST 90501
Certificate Information: 1341 1/2 W 218TH ST 90501
- Application / Permit
- 20016-10000-31253
- Plan Check / Job No.
- B20LA22265
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED A.D.U. AT REAR OF LOT.
- Permit Issued
- Issued on 11/24/2021
- Issuing Office
- Current Status
- CofO Issued on 9/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | JOE VO |
| Corrections Issued | 1/13/2021 | JOE VO |
| Quality Review Completed | 1/29/2021 | MINYE PAK |
| Applicant returned to address corrections | 7/7/2021 | JOE VO |
| Plan Check Approved | 11/5/2021 | JOE VO |
| Issued | 11/24/2021 | APPLICANT |
| CofO in Progress | 7/6/2023 | EUGENE CASSIDY |
| Permit Finaled | 9/29/2023 | ANSON MAGLASANG |
| CofO Issued | 9/29/2023 | ANSON MAGLASANG |
| Permit Finaled | 9/29/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 2/17/2021 | ERIK BEASLEY |
| Permit | Cleared | 3/3/2021 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2021 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 3/4/2021 | ERIK BEASLEY |
| Sewer availability | Cleared | 3/12/2021 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 5/18/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 10/28/2021 | KHAING AYE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/9/2021 | Not Ready for Inspection | JOHN KLARIN |
| Pre-Inspection | 12/9/2021 | Approved | JOHN KLARIN |
| Deputy Drilled-In Anchors | 12/10/2021 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 12/20/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 12/27/2021 | Not Ready for Inspection | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 12/27/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 12/27/2021 | Not Ready for Inspection | JOHN KLARIN |
| Verify Sprinkler Sign Off | 12/27/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 2/9/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 2/9/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Wood Frame | 2/9/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 3/16/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Service/Power Release | 3/16/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/12/2022 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 4/12/2022 | Corrections Issued | EUGENE CASSIDY |
| Insulation | 4/12/2022 | Partial Approval | EUGENE CASSIDY |
| Wood Frame | 4/12/2022 | Partial Approval | EUGENE CASSIDY |
| HVAC-Final | 4/15/2022 | Approved | JOHN KLARIN |
| HVAC-Rough | 4/15/2022 | Approved | JOHN KLARIN |
| Insulation | 4/15/2022 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2022 | Approved | JOHN KLARIN |
| Gas Test | 4/19/2022 | Approved | JOHN KLARIN |
| Insulation | 4/19/2022 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 4/19/2022 | Approved | JOHN KLARIN |
| Drywall Nailing | 4/22/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 4/22/2022 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 4/27/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 4/27/2022 | Approved | EUGENE CASSIDY |
| Sewer | 4/27/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 4/29/2022 | Approved | EUGENE CASSIDY |
| Sewer | 4/29/2022 | Approved | EUGENE CASSIDY |
| Shower Pan | 4/29/2022 | Approved | EUGENE CASSIDY |
| Shower Pan | 5/2/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 5/23/2022 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Final | 5/23/2022 | Corrections Issued | EUGENE CASSIDY |
| Smoke Detectors | 5/23/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/18/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 7/18/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 7/18/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 7/18/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 7/18/2022 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 7/18/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 7/18/2022 | Approved | EUGENE CASSIDY |
| Final | 9/16/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 9/16/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 9/16/2022 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 9/16/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 2/22/2023 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 2/22/2023 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 2/22/2023 | Not Required | EUGENE CASSIDY |
| ELECTRICAL-Final | 6/29/2023 | Approved | EUGENE CASSIDY |
| Final | 6/29/2023 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 6/29/2023 | SGSOV Approved | EUGENE CASSIDY |
| Final | 7/5/2023 | OK to Issue CofO | EUGENE CASSIDY |
| PLUMBING-Final | 7/5/2023 | Approved | EUGENE CASSIDY |