261 1/2 S HUDSON AVE 90004
Certificate Information: 261 1/2 S HUDSON AVE 90004
- Application / Permit
- 20016-10000-31220
- Plan Check / Job No.
- B20LA22231
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE INTO A.D.U. PER STATE LAW.
- Permit Issued
- Issued on 5/20/2021
- Issuing Office
- Current Status
- CofO Issued on 9/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/14/2020 | LAWRENCE QUIRANTE |
| Corrections Issued | 12/15/2020 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 5/7/2021 | RACHEL BEYENE |
| Plan Check Approved | 5/19/2021 | JOSEPH RAFOLS |
| Issued | 5/20/2021 | APPLICANT |
| Building Plans Picked Up | 5/24/2021 | APPLICANT |
| CofO in Progress | 8/25/2023 | ROY SPAULDING |
| No Progress | 9/14/2023 | SCOTT FINNILA |
| CofO in Progress | 9/25/2023 | DEROLD HAUFF |
| CofO Issued | 9/25/2023 | DEROLD HAUFF |
| Permit Finaled | 9/25/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/22/2021 | ELAINE LEI |
| Sewer availability | Cleared | 1/22/2021 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2021 | ELAINE LEI |
| HPOZ | Cleared | 4/29/2021 | SUKI GERSHENHORN |
Contact Information
| Architect | Feld,, Dovid Yitzchak; Lic. No.: C37588 | 921 S HOLT AVENUE LOS ANGELES, CA 90035 |
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 10/4/2021 | Approved | ADAM ESCOTO |
| Special/Order Compliance | 10/26/2021 | Partial Approval | JOSEPH MCGARRY |
| Special/Order Compliance | 11/4/2021 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 1/20/2023 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 1/24/2023 | Partial Approval | RICHARD DOCKUS |
| HVAC-Rough | 1/24/2023 | Approved | RICHARD DOCKUS |
| Insulation | 1/30/2023 | Partial Approval | RICHARD DOCKUS |
| Interior/Exterior Lathing | 1/30/2023 | Partial Approval | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 2/15/2023 | Approved | MICHAEL LEWIS |
| Deputy Wood Construction | 2/15/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2023 | Approved | MICHAEL LEWIS |
| METHANE-Rough | 2/15/2023 | Approved | MICHAEL LEWIS |
| Insulation | 3/6/2023 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 4/28/2023 | Approved | RICHARD DOCKUS |
| Shower Pan | 5/11/2023 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 5/23/2023 | Approved | LILIANA PORTILLO |
| Final | 6/1/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 8/24/2023 | OK to Issue CofO | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 8/24/2023 | SGSOV Approved | ROY SPAULDING |
| Smoke Detectors | 8/24/2023 | Approved | ROY SPAULDING |