2033-2033 1/2 W 41ST PL 90062

Certificate Information: 2033-2033 1/2 W 41ST PL 90062

Application / Permit
20016-10000-31121
Plan Check / Job No.
B20LA22159
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT PORTION OF (E) SINGLE FAMILY DWELLING TO JUNIOR ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) and 65852.22
Permit Issued
Issued on 4/30/2022
Issuing Office
Current Status
Issued on 4/30/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/9/2020 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 DANIEL YIP
Corrections Issued 1/21/2021 DANIEL YIP
Quality Review Completed 2/2/2021 ALLEN MANALANSAN
Applicant returned to address corrections 2/15/2022 DANIEL YIP
Plan Check Approved 3/22/2022 DANIEL YIP
Building Plans Picked Up 3/23/2022 APPLICANT
Issued 4/30/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/3/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/20/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/7/2023 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/11/2023 Partial Approval JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 5/11/2023 Partial Approval JOSEPH MCGARRY
Insulation 5/17/2023 No Access for Inspection DONALD CRICHLOW
Insulation 5/18/2023 Approved STUART CHAPMAN
Drywall Nailing 5/25/2023 Corrections Issued SABAS ALONSO
Drywall Nailing 6/1/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 8/10/2023 Approved SABAS ALONSO
Final 8/10/2023 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 8/10/2023 SGSOV Approved SABAS ALONSO
Smoke Detectors 8/10/2023 Approved SABAS ALONSO
Final 9/6/2023 Conditional Approval CHARLES BOGHOSKHAN