802 S MATEO ST 90021

Certificate Information: 802 S MATEO ST 90021

Application / Permit
20016-10000-31098
Plan Check / Job No.
B20LA22133
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(4) Art Gallery
Work Description
CHANGE OF USE FROM FOOD PROCESSING TO ART GALLERIA (A-3 OCCUPANCY).
Permit Issued
Issued on 10/15/2021
Issuing Office
Current Status
CofO Issued on 11/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 JOE VO
Corrections Issued 12/15/2020 JOE VO
Quality Review Completed 12/24/2020 MINYE PAK
Building Plans Picked Up 12/29/2020 APPLICANT
Plan Check Approved 8/16/2021 JOE VO
Issued 10/15/2021 APPLICANT
CofO in Progress 11/6/2024 RONALD JIMENEZ
CofO Issued 11/7/2024 RAFAEL ESPINOZA
Permit Finaled 11/7/2024 RAFAEL ESPINOZA

Permit Application Clearance Information

Sewer availability Cleared 5/19/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/20/2021 JEANIE LAM
Redevelopment Project Area Cleared 5/27/2021 GRACIELA ACOSTA
Fire Marshall Fire Life Safety Cleared 6/29/2021 MENOA AGHAJANI
Hydrant and Access approval Cleared 7/18/2021 ROBERT DUFF
DAS Clearance Cleared 8/6/2021 ELIZABETH TOMS
Project located in CRA area Cleared 8/16/2021 CRAIG BULLOCK

Contact Information

Architect Sullivan,, Scott Bernard; Lic. No.: C33139 1126 BONILLA DR      TOPANGA, CA 90290
Contractor Almighty Builders Inc; Lic. No.: 1075367-B 133 SOUTH PALM DR APT 5      BEVERLY HILLS, CA 90212

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Final 10/17/2023 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 10/17/2023 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 10/17/2023 Not Ready for Inspection KATY RAMIREZ
Special/Order Compliance 10/17/2023 Not Ready for Inspection RICARDO ROBLES
Final 4/22/2024 Not Ready for Inspection RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 4/22/2024 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 4/22/2024 Approved RONALD JIMENEZ
Final 10/16/2024 Not Ready for Inspection RAMAZANALI ALMASI
Final 11/4/2024 OK to Issue CofO RONALD JIMENEZ