2966-2968 N GLENMANOR PL 90039

Certificate Information: 2966-2968 N GLENMANOR PL 90039

Application / Permit
20016-10000-31038
Plan Check / Job No.
B20LA22075
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT FRONT PORTION (761 SF) OF (E) SFD INTO A.D.U. PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 12/6/2021
Issuing Office
Current Status
CofO Issued on 1/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2021 APPLICANT
Assigned to Plan Check Engineer 4/19/2021 LAWRENCE QUIRANTE
Corrections Issued 4/19/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 8/21/2021 TSE MING HUANG
Applicant returned to address corrections 11/5/2021 JOSEPH RAFOLS
Plan Check Approved 11/29/2021 SHANGQIN XIE
Issued 12/6/2021 APPLICANT
Building Plans Picked Up 12/9/2021 APPLICANT
CofO in Progress 1/18/2023 HAMIK HARTOUNIAN
CofO Issued 1/25/2023 DEROLD HAUFF
Permit Finaled 1/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/15/2021 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 10/15/2021 CHRISTOPHER ROCHA
Sewer availability Cleared 10/15/2021 CHRISTOPHER ROCHA

Contact Information

Contractor Bear River Construction Inc; Lic. No.: 1056134-B 27014 SECO CYN RD      SANTA CLARITA, CA 91350

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/9/2021 Approved CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 1/10/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 1/12/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 1/14/2022 Approved OSVALDO PARAMO
Wood Frame 1/14/2022 Approved OSVALDO PARAMO
Pre-Inspection 8/16/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Rough-Elec/Plmb/HVAC 9/9/2022 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Final 11/21/2022 Approved STUART CHAPMAN
Final 11/21/2022 Corrections Issued STUART CHAPMAN
HVAC-Final 11/21/2022 Approved STUART CHAPMAN
PLUMBING-Final 11/21/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 12/5/2022 Approved HAMIK HARTOUNIAN
Final 12/5/2022 Partial Inspection HAMIK HARTOUNIAN
MERV13>=Final 12/5/2022 Approved HAMIK HARTOUNIAN
MERV13>=Rough 12/5/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 12/5/2022 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 12/5/2022 Approved HAMIK HARTOUNIAN
Final 1/17/2023 OK to Issue CofO HAMIK HARTOUNIAN