1408 S BROCKTON AVE 90025
Certificate Information: 1408 S BROCKTON AVE 90025
- Application / Permit
- 20016-10000-31027
- Plan Check / Job No.
- B20LA22066
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: By adding (1) SSCC at WEST elevation, (1) SSCC at SOUTH elevation and (1) 2-way SSCC box col at NORTH AND EAST elevation.
- Permit Issued
- Issued on 2/3/2022
- Issuing Office
- Current Status
- CofC Issued on 11/10/2022
Permit Application Status History
| Submitted | 12/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2020 | JESSE VIDUYA |
| Corrections Issued | 12/24/2020 | JESSE VIDUYA |
| Quality Review Completed | 12/30/2020 | HANS SANTIAGO |
| Applicant returned to address corrections | 1/26/2021 | JESSE VIDUYA |
| Applicant returned to address corrections | 2/10/2021 | JESSE VIDUYA |
| Plan Check Approved | 2/17/2021 | JESSE VIDUYA |
| Issued | 2/3/2022 | APPLICANT |
| OK for CofC | 10/31/2022 | ALAN NOVAK |
| OK to Issue CofC | 11/1/2022 | HENRY BAGHDASSARIAN |
| CofC Issued | 11/10/2022 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 1/31/2022 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Sks Construction; Lic. No.: 720390-B | 15134 FRIAR STREET VAN NUYS, CA 91411 |
| Engineer | Shaolian,, Shahab Joseph; Lic. No.: C84155 | 5104 GARDEN GROVE TARZANA, CA 91356 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/15/2022 | Approved | ALAN NOVAK |
| Deputy Steel/Welding | 8/4/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 8/5/2022 | Conditional Approval | ALAN NOVAK |
| Footing/Foundation/Slab | 8/8/2022 | Approved | ALAN NOVAK |
| Structural Steel Frame | 8/8/2022 | Approved | ALAN NOVAK |
| Deputy Reinf. Concrete | 8/9/2022 | Conditional Approval | ALAN NOVAK |
| Wood Frame | 8/17/2022 | Approved | ALAN NOVAK |
| Deputy Wood Construction | 8/19/2022 | Conditional Approval | ALAN NOVAK |
| Wood Frame | 8/19/2022 | Approved | ALAN NOVAK |
| Interior/Exterior Lathing | 8/25/2022 | Approved | ALAN NOVAK |
| Final | 10/31/2022 | OK for CofC | ALAN NOVAK |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Approved | ALAN NOVAK |