1110 N LILLIAN WAY 90038
Certificate Information: 1110 N LILLIAN WAY 90038
- Application / Permit
- 20016-10000-31026
- Plan Check / Job No.
- B20LA22065
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: WOOD SHEAR WALLS.
- Permit Issued
- Issued on 1/28/2021
- Issuing Office
- Current Status
- CofC Issued on 8/28/2023
Permit Application Status History
| Submitted | 12/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2020 | VARAND SARKISIAN |
| Corrections Issued | 12/23/2020 | VARAND SARKISIAN |
| Quality Review Completed | 12/28/2020 | DAVID CHANG |
| Plan Check Approved | 1/13/2021 | VARAND SARKISIAN |
| Issued | 1/28/2021 | APPLICANT |
| OK for CofC | 6/20/2023 | DARRYL ARNOLD |
| CofC Issued | 8/28/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 1/27/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Retrofitting360 Inc; Lic. No.: 1039226-B | 19562 VENTURA BLVD# 230 TARZANA, CA 91356 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/25/2021 | Approved | JONATHAN QUACH |
| Pre-Inspection | 3/9/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Footing/Foundation/Slab | 3/12/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Footing/Foundation/Slab | 3/15/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Deputy Wood Construction | 3/19/2021 | Conditional Approval | FRED WOHLFARTH |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Footing/Foundation/Slab | 3/19/2021 | Approved | JONATHAN QUACH |
| Deputy Reinf. Concrete | 3/24/2021 | Conditional Approval | JONATHAN QUACH |
| Reinforced Concrete Frame | 3/26/2021 | Approved | MARK FERRARI |
| Structural Steel Frame | 3/26/2021 | Partial Inspection | MARK FERRARI |
| Wood Frame | 3/26/2021 | Partial Approval | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2021 | Approved | JONATHAN QUACH |
| Structural Steel Frame | 4/5/2021 | Approved | JONATHAN QUACH |
| Wood Frame | 4/5/2021 | Approved | JONATHAN QUACH |
| Deputy Wood Construction | 4/6/2021 | Conditional Approval | JONATHAN QUACH |
| Interior/Exterior Lathing | 4/15/2021 | Approved | JONATHAN QUACH |
| Final | 4/28/2021 | Corrections Issued | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 4/28/2021 | SGSOV Not Ready | JONATHAN QUACH |
| Smoke Detectors | 4/28/2021 | Approved | JONATHAN QUACH |
| Final | 6/20/2023 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 6/20/2023 | SGSOV Approved | DARRYL ARNOLD |