2258 W 28TH ST 90018

Certificate Information: 2258 W 28TH ST 90018

Application / Permit
20016-10000-30825
Plan Check / Job No.
B20LA21966
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN Convert existing detached garage to accessory dwelling unit per state law GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 12/17/2022
Issuing Office
Current Status
CofO Issued on 11/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/1/2020 APPLICANT
Assigned to Plan Check Engineer 12/2/2020 VU NGUYEN
Corrections Issued 12/3/2020 VU NGUYEN
Applicant returned to address corrections 1/19/2021 MONICA RAMIREZ
Applicant returned to address corrections 3/3/2021 MONICA RAMIREZ
Applicant returned to address corrections 3/9/2021 MONICA RAMIREZ
Applicant returned to address corrections 3/16/2021 MONICA RAMIREZ
Plan Check Approved 3/17/2021 MONICA RAMIREZ
No Progress 11/23/2022 MONICA RAMIREZ
Plan Check Approved 11/23/2022 MONICA RAMIREZ
Issued 12/17/2022 APPLICANT
CofO in Progress 11/2/2024 SABAS ALONSO
Permit Finaled 11/10/2024 DEROLD HAUFF
Permit Finaled 11/10/2024 DEROLD HAUFF
CofO Issued 11/10/2024 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 12/7/2020 MAX LODER
Address approval Cleared 12/14/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 12/14/2020 CECILIO NAVARRO
Sewer availability Cleared 12/14/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 12/15/2020 CECILIO NAVARRO
Construction within easement Cleared 3/1/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Chen,, Junfei; Lic. No.: C85841 726 FAMILY TREE      IRVINE, CA 92618

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/18/2023 No Access for Inspection SABAS ALONSO
Pre-Inspection 12/21/2023 Partial Inspection SABAS ALONSO
Footing/Foundation/Slab 1/8/2024 Partial Approval SABAS ALONSO
Sewer 1/8/2024 Approved SABAS ALONSO
Underground Mechanical 1/8/2024 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 1/17/2024 Approved SABAS ALONSO
ELECTRICAL-Rough 2/9/2024 Corrections Issued SABAS ALONSO
PLUMBING-Rough 2/9/2024 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 2/13/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 2/13/2024 Approved SABAS ALONSO
METHANE-Rough 2/13/2024 Approved SABAS ALONSO
PLUMBING-Rough 2/13/2024 Approved SABAS ALONSO
Shower Pan 2/13/2024 Approved SABAS ALONSO
HVAC-Rough 2/21/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 2/21/2024 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 2/22/2024 Approved SABAS ALONSO
Green Building Rough 2/22/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 2/22/2024 Partial Approval SABAS ALONSO
Insulation 2/26/2024 Approved BRENDAN MORELLI
Interior/Exterior Lathing 2/26/2024 Not Ready for Inspection BRENDAN MORELLI
Drywall Nailing 2/29/2024 Approved BRENDAN MORELLI
Interior/Exterior Lathing 2/29/2024 Partial Approval BRENDAN MORELLI
Service/Power Release 8/28/2024 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 8/30/2024 Not Ready for Inspection SABAS ALONSO
Final 8/30/2024 Corrections Issued SABAS ALONSO
HVAC-Final 8/30/2024 Approved SABAS ALONSO
PLUMBING-Final 8/30/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 8/30/2024 SGSOV Approved SABAS ALONSO
Service/Power Release 8/30/2024 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 8/30/2024 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 9/27/2024 Approved SABAS ALONSO
Final 9/27/2024 Corrections Issued SABAS ALONSO
HVAC-Final 9/27/2024 Approved SABAS ALONSO
PLUMBING-Final 9/27/2024 Approved SABAS ALONSO
Smoke Detectors 9/27/2024 Approved SABAS ALONSO
Final 10/29/2024 OK to Issue CofO SABAS ALONSO