2258 W 28TH ST 90018
Certificate Information: 2258 W 28TH ST 90018
- Application / Permit
- 20016-10000-30825
- Plan Check / Job No.
- B20LA21966
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN Convert existing detached garage to accessory dwelling unit per state law GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/17/2022
- Issuing Office
- Current Status
- CofO Issued on 11/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2020 | VU NGUYEN |
| Corrections Issued | 12/3/2020 | VU NGUYEN |
| Applicant returned to address corrections | 1/19/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 3/3/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 3/9/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 3/16/2021 | MONICA RAMIREZ |
| Plan Check Approved | 3/17/2021 | MONICA RAMIREZ |
| No Progress | 11/23/2022 | MONICA RAMIREZ |
| Plan Check Approved | 11/23/2022 | MONICA RAMIREZ |
| Issued | 12/17/2022 | APPLICANT |
| CofO in Progress | 11/2/2024 | SABAS ALONSO |
| Permit Finaled | 11/10/2024 | DEROLD HAUFF |
| Permit Finaled | 11/10/2024 | DEROLD HAUFF |
| CofO Issued | 11/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 12/7/2020 | MAX LODER |
| Address approval | Cleared | 12/14/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 12/14/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 12/14/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2020 | CECILIO NAVARRO |
| Construction within easement | Cleared | 3/1/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chen,, Junfei; Lic. No.: C85841 | 726 FAMILY TREE IRVINE, CA 92618 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/18/2023 | No Access for Inspection | SABAS ALONSO |
| Pre-Inspection | 12/21/2023 | Partial Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 1/8/2024 | Partial Approval | SABAS ALONSO |
| Sewer | 1/8/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 1/8/2024 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 1/17/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 2/9/2024 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 2/9/2024 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 2/13/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Approved | SABAS ALONSO |
| METHANE-Rough | 2/13/2024 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 2/13/2024 | Approved | SABAS ALONSO |
| Shower Pan | 2/13/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 2/21/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 2/21/2024 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 2/22/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 2/22/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 2/22/2024 | Partial Approval | SABAS ALONSO |
| Insulation | 2/26/2024 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 2/26/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Drywall Nailing | 2/29/2024 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 2/29/2024 | Partial Approval | BRENDAN MORELLI |
| Service/Power Release | 8/28/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 8/30/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 8/30/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 8/30/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 8/30/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 8/30/2024 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 8/30/2024 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 8/30/2024 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Final | 9/27/2024 | Approved | SABAS ALONSO |
| Final | 9/27/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 9/27/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 9/27/2024 | Approved | SABAS ALONSO |
| Smoke Detectors | 9/27/2024 | Approved | SABAS ALONSO |
| Final | 10/29/2024 | OK to Issue CofO | SABAS ALONSO |