1014 N WESTERN AVE 90029

Certificate Information: 1014 N WESTERN AVE 90029

Application / Permit
20016-10000-30688
Plan Check / Job No.
B20LA21889
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(18) School - private
Work Description
Tenant Improvement to existing pre school building (17016-10000-09250). Interior scope to include new kitchen millwork and finishes, new finishes at main entry, new partition walls to enclose storage/lounge space, and associated minor adjustments to HVAC and Electrical. Exterior scope includes improved drainage at play area, re-striped parking, and new motorized security gate at alley.
Permit Issued
Issued on 12/15/2021
Issuing Office
Current Status
Permit Finaled on 7/12/2022

Permit Application Status History

Submitted 12/3/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 JOE VO
Corrections Issued 12/13/2020 JOE VO
Quality Review Completed 1/12/2021 MINYE PAK
Applicant returned to address corrections 2/4/2021 JOE VO
Applicant returned to address corrections 2/9/2021 JOE VO
Disabled Access Plans Picked Up 2/10/2021 APPLICANT
Green Plans Picked Up 3/9/2021 APPLICANT
Plan Check Approved 3/16/2021 JOE VO
Plan Check Approved 12/13/2021 JOE VO
Issued 12/15/2021 APPLICANT
Permit Finaled 7/11/2022 JONATHAN QUACH

Permit Application Clearance Information

Green Code Cleared 2/22/2021 JOE VO
DAS Clearance Cleared 3/2/2021 JOE VO

Contact Information

Contractor Builtall; Lic. No.: 785095-B 1323 LINCOLE BLVD STE 230      SANTA MONICA, CA 90401

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/14/2022 Corrections Issued SORIN CIRSTOIU
Footing/Foundation/Slab 1/24/2022 Partial Inspection JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 3/16/2022 Partial Inspection SORIN CIRSTOIU
Special/Order Compliance 3/18/2022 Corrections Issued SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 5/6/2022 SGSOV Not Ready JONATHAN QUACH
Final 5/20/2022 Partial Inspection SORIN CIRSTOIU
Green Building Final 5/20/2022 Partial Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 5/20/2022 SGSOV Approved SORIN CIRSTOIU
Smoke Detectors 5/20/2022 Approved SORIN CIRSTOIU
Final 7/11/2022 Permit Finaled JONATHAN QUACH
Green Building Final 7/11/2022 Approved JONATHAN QUACH