18934-18936 W SYLVAN ST 91335
Certificate Information: 18934-18936 W SYLVAN ST 91335
- Application / Permit
- 20016-10000-30494
- Plan Check / Job No.
- B20LA21772
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- **eplan** Convert existing attached 2 car garage and portion of sfd into an Accessory dwelling unit per LAMC 12.22 A.33 (b)(5)
- Permit Issued
- Issued on 2/8/2021
- Issuing Office
- Current Status
- CofO Issued on 6/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 12/1/2020 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 1/4/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 1/12/2021 | MONICA RAMIREZ |
| Plan Check Approved | 2/5/2021 | MONICA RAMIREZ |
| Issued | 2/8/2021 | APPLICANT |
| CofO in Progress | 6/21/2021 | STEVEN BACK |
| Permit Finaled | 6/22/2021 | JOHN JANSON |
| CofO Issued | 6/22/2021 | JOHN JANSON |
| Permit Finaled | 6/22/2021 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 12/21/2020 | MARITZA PRZEKOP |
| Address approval | Cleared | 12/29/2020 | ABDULLAH SADOZAI |
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2020 | ABDULLAH SADOZAI |
| Sewer availability | Cleared | 12/29/2020 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/5/2021 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 3/5/2021 | Partial Approval | DAVID STEPANYAN |
| Pre-Inspection | 3/5/2021 | Partial Inspection | DAVID STEPANYAN |
| Sewer | 3/5/2021 | Approved | DAVID STEPANYAN |
| Special/Order Compliance | 3/5/2021 | Corrections Issued | DAVID STEPANYAN |
| Underground Mechanical | 3/5/2021 | Partial Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 3/16/2021 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 3/16/2021 | Approved | STEVEN BACK |
| Green Building Rough | 3/16/2021 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 3/16/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 3/23/2021 | Approved | STEVEN BACK |
| Green Building Rough | 3/23/2021 | Approved | STEVEN BACK |
| HVAC-Rough | 3/23/2021 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 3/23/2021 | Partial Approval | STEVEN BACK |
| Insulation | 3/25/2021 | Partial Approval | STEVEN BACK |
| Insulation | 3/26/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 4/1/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/6/2021 | Not Ready for Inspection | STEVEN BACK |
| Shower Pan | 4/6/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 4/12/2021 | Corrections Issued | STEVEN BACK |
| Drywall Nailing | 4/12/2021 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 4/12/2021 | Corrections Issued | STEVEN BACK |
| Insulation | 4/12/2021 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 4/12/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 4/16/2021 | Corrections Issued | STEVEN BACK |
| Drywall Nailing | 4/16/2021 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 4/16/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 4/22/2021 | Approved | STEVEN BACK |
| Insulation | 4/22/2021 | Approved | STEVEN BACK |
| Verify Sprinkler Sign Off | 4/22/2021 | Approved | STEVEN BACK |
| Drywall Nailing | 4/23/2021 | Approved | STEVEN BACK |
| Final | 5/28/2021 | Corrections Issued | PETER FOLLING |
| Green Building Final | 5/28/2021 | Not Ready for Inspection | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 5/28/2021 | SGSOV Not Ready | PETER FOLLING |
| Smoke Detectors | 5/28/2021 | Not Ready for Inspection | PETER FOLLING |
| Final | 6/7/2021 | Corrections Issued | STEVEN BACK |
| Gas Test | 6/7/2021 | Approved | STEVEN BACK |
| Green Building Final | 6/7/2021 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 6/7/2021 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 6/7/2021 | Approved | STEVEN BACK |
| Final | 6/14/2021 | Corrections Issued | STEVEN BACK |
| Final | 6/21/2021 | OK to Issue CofO | STEVEN BACK |