18934-18936 W SYLVAN ST 91335

Certificate Information: 18934-18936 W SYLVAN ST 91335

Application / Permit
20016-10000-30494
Plan Check / Job No.
B20LA21772
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
**eplan** Convert existing attached 2 car garage and portion of sfd into an Accessory dwelling unit per LAMC 12.22 A.33 (b)(5)
Permit Issued
Issued on 2/8/2021
Issuing Office
Current Status
CofO Issued on 6/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2020 APPLICANT
Assigned to Plan Check Engineer 11/30/2020 ARSALAN SHABESTARI
Corrections Issued 12/1/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 1/4/2021 MONICA RAMIREZ
Applicant returned to address corrections 1/12/2021 MONICA RAMIREZ
Plan Check Approved 2/5/2021 MONICA RAMIREZ
Issued 2/8/2021 APPLICANT
CofO in Progress 6/21/2021 STEVEN BACK
Permit Finaled 6/22/2021 JOHN JANSON
CofO Issued 6/22/2021 JOHN JANSON
Permit Finaled 6/22/2021 JOHN JANSON

Permit Application Clearance Information

ZI Cleared 12/21/2020 MARITZA PRZEKOP
Address approval Cleared 12/29/2020 ABDULLAH SADOZAI
Eng Process Fee Ord 176,300 Cleared 12/29/2020 ABDULLAH SADOZAI
Sewer availability Cleared 12/29/2020 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/5/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 3/5/2021 Partial Approval DAVID STEPANYAN
Pre-Inspection 3/5/2021 Partial Inspection DAVID STEPANYAN
Sewer 3/5/2021 Approved DAVID STEPANYAN
Special/Order Compliance 3/5/2021 Corrections Issued DAVID STEPANYAN
Underground Mechanical 3/5/2021 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 3/16/2021 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 3/16/2021 Approved STEVEN BACK
Green Building Rough 3/16/2021 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 3/16/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 3/23/2021 Approved STEVEN BACK
Green Building Rough 3/23/2021 Approved STEVEN BACK
HVAC-Rough 3/23/2021 Approved STEVEN BACK
Interior/Exterior Lathing 3/23/2021 Partial Approval STEVEN BACK
Insulation 3/25/2021 Partial Approval STEVEN BACK
Insulation 3/26/2021 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 4/1/2021 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 4/6/2021 Not Ready for Inspection STEVEN BACK
Shower Pan 4/6/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 4/12/2021 Corrections Issued STEVEN BACK
Drywall Nailing 4/12/2021 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 4/12/2021 Corrections Issued STEVEN BACK
Insulation 4/12/2021 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 4/12/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 4/16/2021 Corrections Issued STEVEN BACK
Drywall Nailing 4/16/2021 Partial Approval STEVEN BACK
ELECTRICAL-Rough 4/16/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 4/22/2021 Approved STEVEN BACK
Insulation 4/22/2021 Approved STEVEN BACK
Verify Sprinkler Sign Off 4/22/2021 Approved STEVEN BACK
Drywall Nailing 4/23/2021 Approved STEVEN BACK
Final 5/28/2021 Corrections Issued PETER FOLLING
Green Building Final 5/28/2021 Not Ready for Inspection PETER FOLLING
SGSOV-Seismic Gas S/O Valve 5/28/2021 SGSOV Not Ready PETER FOLLING
Smoke Detectors 5/28/2021 Not Ready for Inspection PETER FOLLING
Final 6/7/2021 Corrections Issued STEVEN BACK
Gas Test 6/7/2021 Approved STEVEN BACK
Green Building Final 6/7/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/7/2021 SGSOV Approved STEVEN BACK
Smoke Detectors 6/7/2021 Approved STEVEN BACK
Final 6/14/2021 Corrections Issued STEVEN BACK
Final 6/21/2021 OK to Issue CofO STEVEN BACK