1134 S CARMONA AVE 90019

Certificate Information: 1134 S CARMONA AVE 90019

Application / Permit
20016-10000-30450
Plan Check / Job No.
B20LA21735
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Ground floor addition to (E) detached garage and conversion of entire building to an ADU. Detached ADU per LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 1/23/2023
Issuing Office
Current Status
CofO Issued on 1/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 SAMUEL GONZALEZ
Corrections Issued 12/11/2020 HELEN NGUYEN
Applicant returned to address corrections 7/29/2021 HELEN NGUYEN
Applicant returned to address corrections 8/12/2022 SAMUEL GONZALEZ
Applicant returned to address corrections 8/31/2022 LAWRENCE QUIRANTE
Plan Check Approved 9/27/2022 SAMUEL GONZALEZ
Issued 1/23/2023 APPLICANT
CofO in Progress 1/23/2024 RICHARD DOCKUS
Permit Finaled 1/30/2024 DEROLD HAUFF
CofO Issued 1/30/2024 DEROLD HAUFF
Permit Finaled 1/30/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/31/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 3/31/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 4/14/2021 PAMELA TENEZA
Sewer availability Cleared 4/14/2021 PAMELA TENEZA
HPOZ Cleared 6/29/2021 CHRISTINA PARK
Miscellaneous Cleared 6/29/2021 CHRISTINA PARK

Contact Information

Contractor Sidekick Homes Llc; Lic. No.: 1098013-B       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/10/2023 Approved RICHARD DOCKUS
Deputy Drilled-In Anchors 5/18/2023 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 5/26/2023 Corrections Issued RICHARD DOCKUS
METHANE-Barrier 5/26/2023 Approved RICHARD DOCKUS
METHANE-Subgrade 5/26/2023 Approved RICHARD DOCKUS
PLUMBING-Rough 5/26/2023 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 6/1/2023 Approved RICHARD DOCKUS
PLUMBING-Rough 6/1/2023 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Partial Approval ALIZAH MAYAGOITIA
Green Building Rough 6/28/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
METHANE-Rough 6/28/2023 Approved ALIZAH MAYAGOITIA
Sewer 7/11/2023 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 7/18/2023 Partial Approval LILIANA PORTILLO
Sewer 7/18/2023 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 7/27/2023 Corrections Issued SCOTT FINNILA
Rough-Elec/Plmb/HVAC 7/27/2023 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 8/1/2023 Approved SCOTT FINNILA
Green Building Rough 8/1/2023 Approved SCOTT FINNILA
Rough-Elec/Plmb/HVAC 8/1/2023 Approved SCOTT FINNILA
Wood Frame 8/1/2023 Approved SCOTT FINNILA
Interior/Exterior Lathing 8/10/2023 Partial Approval LILIANA PORTILLO
Shower Pan 8/10/2023 Approved LILIANA PORTILLO
Insulation 8/21/2023 Approved ROY SPAULDING
Drywall Nailing 9/1/2023 Approved ROY SPAULDING
Final 12/19/2023 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 12/19/2023 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 12/19/2023 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 12/19/2023 Approved JOAQUIN GREENOUGH
Final 12/29/2023 Corrections Issued RICHARD DOCKUS
Green Building Final 12/29/2023 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 12/29/2023 SGSOV Not Ready RICHARD DOCKUS
Final 1/5/2024 OK to Issue CofO RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 1/5/2024 SGSOV Approved RICHARD DOCKUS