1134 S CARMONA AVE 90019
Certificate Information: 1134 S CARMONA AVE 90019
- Application / Permit
- 20016-10000-30450
- Plan Check / Job No.
- B20LA21735
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Ground floor addition to (E) detached garage and conversion of entire building to an ADU. Detached ADU per LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 1/23/2023
- Issuing Office
- Current Status
- CofO Issued on 1/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | SAMUEL GONZALEZ |
| Corrections Issued | 12/11/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 7/29/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 8/12/2022 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 8/31/2022 | LAWRENCE QUIRANTE |
| Plan Check Approved | 9/27/2022 | SAMUEL GONZALEZ |
| Issued | 1/23/2023 | APPLICANT |
| CofO in Progress | 1/23/2024 | RICHARD DOCKUS |
| Permit Finaled | 1/30/2024 | DEROLD HAUFF |
| CofO Issued | 1/30/2024 | DEROLD HAUFF |
| Permit Finaled | 1/30/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/31/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 3/31/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2021 | PAMELA TENEZA |
| Sewer availability | Cleared | 4/14/2021 | PAMELA TENEZA |
| HPOZ | Cleared | 6/29/2021 | CHRISTINA PARK |
| Miscellaneous | Cleared | 6/29/2021 | CHRISTINA PARK |
Contact Information
| Contractor | Sidekick Homes Llc; Lic. No.: 1098013-B | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/10/2023 | Approved | RICHARD DOCKUS |
| Deputy Drilled-In Anchors | 5/18/2023 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 5/26/2023 | Corrections Issued | RICHARD DOCKUS |
| METHANE-Barrier | 5/26/2023 | Approved | RICHARD DOCKUS |
| METHANE-Subgrade | 5/26/2023 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 5/26/2023 | Corrections Issued | RICHARD DOCKUS |
| Footing/Foundation/Slab | 6/1/2023 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 6/1/2023 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Rough | 6/28/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| METHANE-Rough | 6/28/2023 | Approved | ALIZAH MAYAGOITIA |
| Sewer | 7/11/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 7/18/2023 | Partial Approval | LILIANA PORTILLO |
| Sewer | 7/18/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2023 | Corrections Issued | SCOTT FINNILA |
| Rough-Elec/Plmb/HVAC | 7/27/2023 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 8/1/2023 | Approved | SCOTT FINNILA |
| Green Building Rough | 8/1/2023 | Approved | SCOTT FINNILA |
| Rough-Elec/Plmb/HVAC | 8/1/2023 | Approved | SCOTT FINNILA |
| Wood Frame | 8/1/2023 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 8/10/2023 | Partial Approval | LILIANA PORTILLO |
| Shower Pan | 8/10/2023 | Approved | LILIANA PORTILLO |
| Insulation | 8/21/2023 | Approved | ROY SPAULDING |
| Drywall Nailing | 9/1/2023 | Approved | ROY SPAULDING |
| Final | 12/19/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 12/19/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 12/19/2023 | Approved | JOAQUIN GREENOUGH |
| Final | 12/29/2023 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 12/29/2023 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 12/29/2023 | SGSOV Not Ready | RICHARD DOCKUS |
| Final | 1/5/2024 | OK to Issue CofO | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 1/5/2024 | SGSOV Approved | RICHARD DOCKUS |