15757 W FOOTHILL BLVD 91342

Certificate Information: 15757 W FOOTHILL BLVD 91342

Application / Permit
20016-10000-30444
Plan Check / Job No.
B20LA21731
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Conversion of (E) detached 2-car garage into an ADU per per state law GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 2/18/2021
Issuing Office
Current Status
CofO Issued on 2/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2020 APPLICANT
Assigned to Plan Check Engineer 12/1/2020 LARRY LEE
Corrections Issued 12/2/2020 LARRY LEE
Applicant returned to address corrections 12/29/2020 MONICA RAMIREZ
Applicant returned to address corrections 1/5/2021 HELEN NGUYEN
Applicant returned to address corrections 1/23/2021 ARSALAN SHABESTARI
Plan Check Approved 2/11/2021 LARRY LEE
No Progress 2/11/2021 LARRY LEE
Issued 2/18/2021 APPLICANT
CofO in Progress 1/26/2022 JOHN HAYES
Permit Finaled 2/23/2022 MICHAEL SMITH
CofO Issued 2/23/2022 MICHAEL SMITH
Permit Finaled 2/23/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/15/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 12/15/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 12/17/2020 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 1/11/2021 BARTON HOLMES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 2/23/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 2/23/2021 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 2/23/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 2/23/2021 Corrections Issued MISAEL ESPARZA
Gas Test 2/23/2021 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 2/23/2021 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 2/23/2021 Partial Approval MISAEL ESPARZA
Underground Mechanical 2/23/2021 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 3/31/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 3/31/2021 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 3/31/2021 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 5/12/2021 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 5/12/2021 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 5/12/2021 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/12/2021 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 5/12/2021 Not Ready for Inspection MISAEL ESPARZA
Gas Test 5/12/2021 Corrections Issued MISAEL ESPARZA
HVAC-Rough 5/12/2021 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 5/12/2021 Approved MISAEL ESPARZA
PLUMBING-Rough 5/12/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 5/18/2021 Approved MISAEL ESPARZA
Gas Test 5/18/2021 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 5/18/2021 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 5/24/2021 Partial Approval MICHAEL TEMPLE
ELECTRICAL-Rough 5/24/2021 Partial Approval MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 5/24/2021 Partial Approval MICHAEL TEMPLE
Gas Test 5/24/2021 Approved MICHAEL TEMPLE
HVAC-Rough 5/24/2021 Approved MICHAEL TEMPLE
Interior/Exterior Lathing 5/24/2021 Partial Inspection MICHAEL TEMPLE
PLUMBING-Rough 5/24/2021 Approved MICHAEL TEMPLE
ELECTRICAL-Rough 6/1/2021 Approved MISAEL ESPARZA
HVAC-Rough 6/1/2021 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 6/3/2021 Approved MISAEL ESPARZA
Insulation 6/3/2021 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 6/3/2021 Partial Approval MICHAEL TEMPLE
BUILDING-Rough-Frame 6/24/2021 Approved MICHAEL TEMPLE
Insulation 6/24/2021 Approved MICHAEL TEMPLE
Rough-Elec/Plmb/HVAC 6/24/2021 Approved MICHAEL TEMPLE
Drywall Nailing 8/3/2021 Approved WILLIAM WREN
Interior/Exterior Lathing 8/17/2021 Partial Approval ADAM ESCOTO
Shower Pan 8/17/2021 Approved ADAM ESCOTO
Final 11/18/2021 Corrections Issued JOHN HAYES
MERV13>=Final 11/18/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 11/18/2021 SGSOV Not Ready JOHN HAYES
Smoke Detectors 11/18/2021 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 12/27/2021 Not Ready for Inspection JOHN HAYES
Final 12/27/2021 Corrections Issued JOHN HAYES
HVAC-Final 12/27/2021 Not Ready for Inspection JOHN HAYES
MERV13>=Final 12/27/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 12/27/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 12/27/2021 SGSOV Not Ready JOHN HAYES
Service/Power Release 12/27/2021 Not Ready for Inspection JOHN HAYES
Smoke Detectors 12/27/2021 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 1/6/2022 Not Ready for Inspection JOHN HAYES
Final 1/6/2022 Corrections Issued JOHN HAYES
HVAC-Final 1/6/2022 Not Ready for Inspection JOHN HAYES
MERV13>=Final 1/6/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 1/6/2022 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 1/6/2022 SGSOV Not Ready JOHN HAYES
Service/Power Release 1/6/2022 Not Ready for Inspection JOHN HAYES
Smoke Detectors 1/6/2022 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 1/14/2022 Not Ready for Inspection JOHN HAYES
Final 1/14/2022 Not Ready for Inspection JOHN HAYES
HVAC-Final 1/14/2022 Not Ready for Inspection JOHN HAYES
MERV13>=Final 1/14/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 1/14/2022 Not Ready for Inspection JOHN HAYES
Pre-Inspection 1/14/2022 Not Ready for Inspection JOHN HAYES
Pre-Inspection 1/14/2022 Partial Inspection MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 1/14/2022 SGSOV Not Ready JOHN HAYES
Service/Power Release 1/14/2022 Not Ready for Inspection JOHN HAYES
Smoke Detectors 1/14/2022 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 1/25/2022 Approved JOHN HAYES
Final 1/25/2022 OK to Issue CofO JOHN HAYES
HVAC-Final 1/25/2022 Approved JOHN HAYES
MERV13>=Final 1/25/2022 Approved JOHN HAYES
PLUMBING-Final 1/25/2022 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 1/25/2022 SGSOV Approved JOHN HAYES
Service/Power Release 1/25/2022 Approved JOHN HAYES
Smoke Detectors 1/25/2022 Approved JOHN HAYES