1641 S CRENSHAW BLVD 90019
Certificate Information: 1641 S CRENSHAW BLVD 90019
- Application / Permit
- 20016-10000-30160
- Plan Check / Job No.
- B20LA21586
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- 1)CONVERSION OF (E) BASEMENT TO ADU WITHIN AN EXISTING APARTMENT 2)CONVERSION OF (E) 2ND FLOOR STORAGE TO ADU WITHIN AN EXISTING APARTMENT
- Permit Issued
- Issued on 10/5/2021
- Issuing Office
- Current Status
- CofO Issued on 6/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | CARLOS MONTES |
| Corrections Issued | 12/28/2020 | CARLOS MONTES |
| Quality Review Completed | 1/13/2021 | TU HUA |
| Applicant returned to address corrections | 3/18/2021 | CARLOS MONTES |
| Disabled Access Plans Picked Up | 6/2/2021 | APPLICANT |
| Green Plans Picked Up | 8/25/2021 | APPLICANT |
| Plan Check Approved | 9/2/2021 | CARLOS MONTES |
| Issued | 10/5/2021 | APPLICANT |
| Building Plans Picked Up | 10/6/2021 | APPLICANT |
| CofO in Progress | 6/18/2024 | DARRYL ARNOLD |
| CofO in Progress | 6/28/2024 | ERNESTO CORRAL |
| Permit Finaled | 6/28/2024 | ERNESTO CORRAL |
| CofO Issued | 6/28/2024 | ERNESTO CORRAL |
| Permit Finaled | 6/28/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2021 | CELINA MORENO |
| Sewer availability | Cleared | 3/5/2021 | CELINA MORENO |
| DAS Clearance | Cleared | 6/3/2021 | CARLOS MONTES |
| Fire Marshal Fire Life Safety | Cleared | 6/14/2021 | MENOA AGHAJANI |
| Green Code | Cleared | 6/14/2021 | AARON COSTA |
| Tenant Habitability Plan | Cleared | 8/10/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Carlen Construction Inc; Lic. No.: 1038498-B | 728 B GRANDVIEW COVINA, CA 91723 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 2/15/2022 | Approved | KATY RAMIREZ |
| METHANE-Rough | 2/15/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Wood Frame | 2/15/2022 | Not Ready for Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 3/9/2023 | SGSOV Not Ready | ALFREDO LOPEZ |
| Final | 6/13/2023 | Corrections Issued | ALFREDO LOPEZ |
| Green Building Final | 6/13/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| METHANE-Final | 6/13/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| METHANE-Rough | 6/13/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/13/2023 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 6/13/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 6/13/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| METHANE-Rough | 10/10/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 10/10/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| METHANE-Rough | 10/31/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 10/31/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| METHANE-Rough | 11/7/2023 | Not Ready for Inspection | JACOB MYERS |
| Wood Frame | 11/7/2023 | Partial Inspection | JACOB MYERS |
| Interior/Exterior Lathing | 11/29/2023 | Not Ready for Inspection | RICARDO ROBLES |
| Interior/Exterior Lathing | 11/30/2023 | Partial Approval | JACOB MYERS |
| Final | 1/22/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Final | 1/22/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| METHANE-Final | 1/22/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| METHANE-Rough | 1/22/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 1/22/2024 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 1/22/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 1/22/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/29/2024 | SGSOV Not Ready | RONALD JIMENEZ |
| Final | 5/7/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Final | 5/7/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| METHANE-Final | 5/7/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| METHANE-Rough | 5/7/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/7/2024 | SGSOV Not Required | ALFREDO LOPEZ |
| Smoke Detectors | 5/7/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 5/7/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 5/21/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Green Building Final | 5/21/2024 | Conditional Approval | DARRYL ARNOLD |
| METHANE-Final | 5/21/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Rough | 5/21/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Smoke Detectors | 5/21/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Wood Frame | 5/21/2024 | Conditional Approval | DARRYL ARNOLD |
| Final | 6/18/2024 | OK to Issue CofO | DARRYL ARNOLD |
| Green Building Final | 6/18/2024 | Approved | DARRYL ARNOLD |
| METHANE-Final | 6/18/2024 | Approved | DARRYL ARNOLD |
| METHANE-Rough | 6/18/2024 | Approved | DARRYL ARNOLD |
| Smoke Detectors | 6/18/2024 | Approved | DARRYL ARNOLD |
| Wood Frame | 6/18/2024 | Approved | DARRYL ARNOLD |