5050 N TUJUNGA AVE 91601
Certificate Information: 5050 N TUJUNGA AVE 91601
- Application / Permit
- 20016-10000-30087
- Plan Check / Job No.
- B20LA21549
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: SOFT STORY SEISMIC REINFORCEMENT AT BUILDING PARKING GARAGE USING (3) CANTILEVERED COLUMNS WITH GRADE BEAMS.
- Permit Issued
- Issued on 4/14/2021
- Issuing Office
- Current Status
- CofC Issued on 10/21/2021
Permit Application Status History
| Submitted | 11/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | JESSE VIDUYA |
| Corrections Issued | 12/17/2020 | JESSE VIDUYA |
| Quality Review Completed | 12/23/2020 | HANS SANTIAGO |
| Applicant returned to address corrections | 1/26/2021 | JESSE VIDUYA |
| Plan Check Approved | 2/10/2021 | JESSE VIDUYA |
| Issued | 4/14/2021 | APPLICANT |
| OK for CofC | 10/19/2021 | KENNETH ROBERTS |
| CofC Issued | 10/21/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 1/20/2021 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 2/2/2021 | DAVID URITA |
| Tenant Habitability Plan | Cleared | 3/17/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Sturdy Builds Inc; Lic. No.: 1006879-B | 21300 VICTORY BLVD SUITE 635 WOODLAND HILLS, CA 91367 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/22/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2021 | Partial Approval | JOE VELASQUEZ |
| Wood Frame | 7/20/2021 | Partial Approval | JOE VELASQUEZ |
| Deputy Wood Construction | 7/21/2021 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 7/22/2021 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 7/22/2021 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 7/23/2021 | No Access for Inspection | JOE VELASQUEZ |
| Insulation | 7/23/2021 | Partial Approval | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 7/26/2021 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Other (see comments) | 8/20/2021 | Conditional Approval | BRUCE CAMPBELL |
| Footing/Foundation/Slab | 8/20/2021 | Approved | BRUCE CAMPBELL |
| Structural Steel Frame | 8/20/2021 | Approved | BRUCE CAMPBELL |
| Wood Frame | 8/20/2021 | Approved | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 8/30/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 8/31/2021 | Conditional Approval | JOE VELASQUEZ |
| Final | 9/23/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/23/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 9/23/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 10/18/2021 | Partial Approval | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 10/18/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 10/18/2021 | Approved | KENNETH ROBERTS |
| Final | 10/19/2021 | OK for CofC | KENNETH ROBERTS |