8942 S DENKER AVE 90047

Certificate Information: 8942 S DENKER AVE 90047

Application / Permit
20016-10000-30013
Plan Check / Job No.
B20LA21523
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN. Convert 18'x18' garage plus 327.7 s.f. addition to A.D.U.
Permit Issued
Issued on 3/12/2021
Issuing Office
Current Status
CofO Issued on 10/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/1/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 ARSALAN SHABESTARI
Corrections Issued 1/13/2021 ARSALAN SHABESTARI
Quality Review Completed 2/2/2021 HERNAN ARREOLA
Plan Check Approved 3/8/2021 ARSALAN SHABESTARI
Issued 3/12/2021 APPLICANT
CofO in Progress 8/13/2022 ENRIQUE MIRELES
CofO in Progress 8/13/2022 ENRIQUE MIRELES
Permit Finaled 10/1/2022 DEROLD HAUFF
CofO Issued 10/1/2022 DEROLD HAUFF
Permit Finaled 10/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/21/2021 THOMAS LANG
Roof/Waste drainage to street Cleared 1/21/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 1/22/2021 THOMAS LANG
Sewer availability Cleared 1/27/2021 THOMAS LANG

Contact Information

Contractor All In One Construction; Lic. No.: 674782-B 1056 CYPRESS AVENUE #H      LA HABRA, CA 90631
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/7/2021 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 4/7/2021 Partial Approval FREDDIE RIVERA
Deputy Drilled-In Anchors 4/16/2021 Approved FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 4/16/2021 Approved FREDDIE RIVERA
Footing/Foundation/Slab 4/16/2021 Approved FREDDIE RIVERA
Footing/Foundation/Slab 4/19/2021 Approved FREDDIE RIVERA
Footing/Foundation/Slab 4/21/2021 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/10/2021 Corrections Issued EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 6/21/2021 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 6/30/2021 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/30/2021 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 6/30/2021 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 7/6/2021 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 7/6/2021 Partial Approval FREDDIE RIVERA
Interior/Exterior Lathing 7/22/2021 Partial Approval JESUS PINEDA
Insulation 8/31/2021 Partial Inspection JESUS PINEDA
BUILDING-Rough-Frame 9/3/2021 Not Ready for Inspection FREDDIE RIVERA
Green Building Rough 9/3/2021 Corrections Issued FREDDIE RIVERA
HVAC-Rough 9/3/2021 Not Ready for Inspection FREDDIE RIVERA
Insulation 9/3/2021 Not Ready for Inspection FREDDIE RIVERA
Wood Frame 9/3/2021 Not Ready for Inspection FREDDIE RIVERA
HVAC-Rough 9/17/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 9/17/2021 Approved FREDDIE RIVERA
Drywall Nailing 9/28/2021 Corrections Issued ALAN MORELOS
BUILDING-Rough-Frame 9/30/2021 Approved FREDDIE RIVERA
Drywall Nailing 9/30/2021 Approved FREDDIE RIVERA
Green Building Rough 9/30/2021 Approved FREDDIE RIVERA
Insulation 9/30/2021 Approved FREDDIE RIVERA
ELECTRICAL-Final 2/14/2022 Not Ready for Inspection FREDDIE RIVERA
HVAC-Final 2/14/2022 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Final 2/14/2022 Not Ready for Inspection FREDDIE RIVERA
Service/Power Release 3/4/2022 Corrections Issued FREDDIE RIVERA
Final 5/19/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 5/19/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 5/19/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 5/19/2022 Approved ENRIQUE MIRELES
Service/Power Release 7/5/2022 Approved ENRIQUE MIRELES
Final 8/1/2022 Corrections Issued ENRIQUE MIRELES
Final 8/11/2022 OK to Issue CofO ENRIQUE MIRELES