8942 S DENKER AVE 90047
Certificate Information: 8942 S DENKER AVE 90047
- Application / Permit
- 20016-10000-30013
- Plan Check / Job No.
- B20LA21523
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. Convert 18'x18' garage plus 327.7 s.f. addition to A.D.U.
- Permit Issued
- Issued on 3/12/2021
- Issuing Office
- Current Status
- CofO Issued on 10/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 1/13/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 2/2/2021 | HERNAN ARREOLA |
| Plan Check Approved | 3/8/2021 | ARSALAN SHABESTARI |
| Issued | 3/12/2021 | APPLICANT |
| CofO in Progress | 8/13/2022 | ENRIQUE MIRELES |
| CofO in Progress | 8/13/2022 | ENRIQUE MIRELES |
| Permit Finaled | 10/1/2022 | DEROLD HAUFF |
| CofO Issued | 10/1/2022 | DEROLD HAUFF |
| Permit Finaled | 10/1/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/21/2021 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 1/21/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2021 | THOMAS LANG |
| Sewer availability | Cleared | 1/27/2021 | THOMAS LANG |
Contact Information
| Contractor | All In One Construction; Lic. No.: 674782-B | 1056 CYPRESS AVENUE #H LA HABRA, CA 90631 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/7/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 4/7/2021 | Partial Approval | FREDDIE RIVERA |
| Deputy Drilled-In Anchors | 4/16/2021 | Approved | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 4/16/2021 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 4/16/2021 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 4/19/2021 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 4/21/2021 | Corrections Issued | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2021 | Corrections Issued | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2021 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 6/30/2021 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 6/30/2021 | Corrections Issued | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2021 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 7/6/2021 | Partial Approval | FREDDIE RIVERA |
| Interior/Exterior Lathing | 7/22/2021 | Partial Approval | JESUS PINEDA |
| Insulation | 8/31/2021 | Partial Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 9/3/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 9/3/2021 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Rough | 9/3/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Insulation | 9/3/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Wood Frame | 9/3/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Rough | 9/17/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 9/17/2021 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 9/28/2021 | Corrections Issued | ALAN MORELOS |
| BUILDING-Rough-Frame | 9/30/2021 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 9/30/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 9/30/2021 | Approved | FREDDIE RIVERA |
| Insulation | 9/30/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 2/14/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Final | 2/14/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Final | 2/14/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Service/Power Release | 3/4/2022 | Corrections Issued | FREDDIE RIVERA |
| Final | 5/19/2022 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 5/19/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 5/19/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 5/19/2022 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 7/5/2022 | Approved | ENRIQUE MIRELES |
| Final | 8/1/2022 | Corrections Issued | ENRIQUE MIRELES |
| Final | 8/11/2022 | OK to Issue CofO | ENRIQUE MIRELES |