2487 W LOY LANE 90041
Certificate Information: 2487 W LOY LANE 90041
- Application / Permit
- 20016-10000-29898
- Plan Check / Job No.
- B20LA21437
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* CONVERSION OF (E) GARAGE/REC-ROOM/ LAUNDRY ROOM TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2 (e)(1)(A)
- Permit Issued
- Issued on 11/10/2021
- Issuing Office
- Current Status
- Issued on 11/10/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/19/2020 | LAMAR DAVIS |
| Corrections Issued | 11/19/2020 | LAMAR DAVIS |
| Applicant returned to address corrections | 4/9/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 5/20/2021 | LAMAR DAVIS |
| Plan Check Approved | 6/14/2021 | MONICA RAMIREZ |
| Issued | 11/10/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2021 | ROSA SILVA |
| Sewer availability | Cleared | 3/4/2021 | ROSA SILVA |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2021 | ROSA SILVA |
| Grading Pre-Inspection | Cleared | 4/5/2021 | PATRICK MISCHLICH |
Contact Information
| Contractor | J A Enterprises Inc; Lic. No.: 981375-B | 4531 GUNDRY AVENUE LONG BEACH, CA 90807 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/26/2022 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 1/28/2022 | Partial Approval | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 2/9/2022 | Conditional Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 2/10/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 3/1/2022 | Corrections Issued | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 3/11/2022 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 3/11/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 3/11/2022 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 3/11/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 3/18/2022 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 3/30/2022 | Approved | CHARLES BOGHOSKHAN |
| SGSOV-Seismic Gas S/O Valve | 4/25/2022 | SGSOV Not Ready | CRAIG VAUGHAN |
| Final | 4/27/2022 | Corrections Issued | CRAIG VAUGHAN |
| Smoke Detectors | 4/27/2022 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/2/2022 | Approved | CRAIG VAUGHAN |
| Final | 5/2/2022 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 5/2/2022 | Approved | CRAIG VAUGHAN |
| Green Building Final | 5/2/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 5/2/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/2/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Final | 6/29/2022 | Corrections Issued | CRAIG VAUGHAN |