2487 W LOY LANE 90041

Certificate Information: 2487 W LOY LANE 90041

Application / Permit
20016-10000-29898
Plan Check / Job No.
B20LA21437
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN CHECK* CONVERSION OF (E) GARAGE/REC-ROOM/ LAUNDRY ROOM TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2 (e)(1)(A)
Permit Issued
Issued on 11/10/2021
Issuing Office
Current Status
Issued on 11/10/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/18/2020 APPLICANT
Assigned to Plan Check Engineer 11/19/2020 LAMAR DAVIS
Corrections Issued 11/19/2020 LAMAR DAVIS
Applicant returned to address corrections 4/9/2021 LAMAR DAVIS
Applicant returned to address corrections 5/20/2021 LAMAR DAVIS
Plan Check Approved 6/14/2021 MONICA RAMIREZ
Issued 11/10/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/4/2021 ROSA SILVA
Sewer availability Cleared 3/4/2021 ROSA SILVA
Eng Process Fee Ord 176,300 Cleared 3/5/2021 ROSA SILVA
Grading Pre-Inspection Cleared 4/5/2021 PATRICK MISCHLICH

Contact Information

Contractor J A Enterprises Inc; Lic. No.: 981375-B 4531 GUNDRY AVENUE      LONG BEACH, CA 90807

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/26/2022 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 1/28/2022 Partial Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 2/9/2022 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 2/10/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 3/1/2022 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 3/11/2022 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 3/11/2022 Approved CRAIG VAUGHAN
HVAC-Rough 3/11/2022 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 3/11/2022 Approved CRAIG VAUGHAN
Insulation 3/18/2022 Approved CHARLES BOGHOSKHAN
Drywall Nailing 3/30/2022 Approved CHARLES BOGHOSKHAN
SGSOV-Seismic Gas S/O Valve 4/25/2022 SGSOV Not Ready CRAIG VAUGHAN
Final 4/27/2022 Corrections Issued CRAIG VAUGHAN
Smoke Detectors 4/27/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 5/2/2022 Approved CRAIG VAUGHAN
Final 5/2/2022 Corrections Issued CRAIG VAUGHAN
Gas Test 5/2/2022 Approved CRAIG VAUGHAN
Green Building Final 5/2/2022 Approved CRAIG VAUGHAN
Green Building Rough 5/2/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 5/2/2022 SGSOV Approved CRAIG VAUGHAN
Final 6/29/2022 Corrections Issued CRAIG VAUGHAN