14203 W GAIN ST 91331

Certificate Information: 14203 W GAIN ST 91331

Application / Permit
20016-10000-29741
Plan Check / Job No.
B20LA21297
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert Existing detached garage to an Accessory dwelling unit per LAMC 12.22A.33(b)(5)
Permit Issued
Issued on 3/19/2021
Issuing Office
Current Status
CofO Issued on 7/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2020 APPLICANT
Assigned to Plan Check Engineer 11/19/2020 JOE VO
Corrections Issued 11/19/2020 JOE VO
Applicant returned to address corrections 2/13/2021 ARSALAN SHABESTARI
Plan Check Approved 3/15/2021 MONICA RAMIREZ
Issued 3/19/2021 APPLICANT
CofO in Progress 6/24/2022 MICKEY YAMASHITA
CofO in Progress 6/24/2022 MICKEY YAMASHITA
CofO Issued 7/28/2022 DAVID JAMES
Permit Finaled 7/28/2022 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 12/3/2020 ADRIAN CASTRO
Sewer availability Cleared 12/3/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/9/2020 ABDULLAH SADOZAI
Construction near power lines Cleared 2/4/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 4/5/2021 Corrections Issued MICKEY YAMASHITA
HVAC-Rough 4/5/2021 Corrections Issued MICKEY YAMASHITA
PLUMBING-Rough 4/5/2021 Corrections Issued MICKEY YAMASHITA
Pre-Inspection 4/5/2021 Corrections Issued MICKEY YAMASHITA
BUILDING-Rough-Frame 5/27/2021 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 5/27/2021 Corrections Issued MICKEY YAMASHITA
Green Building Rough 5/27/2021 Not Ready for Inspection MICKEY YAMASHITA
PLUMBING-Rough 5/27/2021 Corrections Issued MICKEY YAMASHITA
Shower Pan 5/27/2021 Approved MICKEY YAMASHITA
ELECTRICAL-Rough 6/10/2021 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 6/10/2021 Approved MICKEY YAMASHITA
Gas Test 6/10/2021 Partial Approval MICKEY YAMASHITA
HVAC-Rough 6/10/2021 Corrections Issued MICKEY YAMASHITA
PLUMBING-Rough 6/10/2021 Corrections Issued MICKEY YAMASHITA
Sewer 6/10/2021 Corrections Issued MICKEY YAMASHITA
Smoke Detectors 6/10/2021 Not Ready for Inspection MICKEY YAMASHITA
Floor/Roof Diaphrgm/Shear Wall 7/6/2021 Corrections Issued MICKEY YAMASHITA
PLUMBING-Rough 7/6/2021 Approved MICKEY YAMASHITA
Floor/Roof Diaphrgm/Shear Wall 7/12/2021 Corrections Issued MICKEY YAMASHITA
Green Building Rough 7/12/2021 Corrections Issued MICKEY YAMASHITA
HVAC-Rough 7/12/2021 Corrections Issued MICKEY YAMASHITA
BUILDING-Rough-Frame 7/14/2021 Approved MICKEY YAMASHITA
ELECTRICAL-Rough 7/14/2021 Approved MICKEY YAMASHITA
Floor/Roof Diaphrgm/Shear Wall 7/14/2021 Approved MICKEY YAMASHITA
Green Building Rough 7/14/2021 Approved MICKEY YAMASHITA
HVAC-Rough 7/14/2021 Approved MICKEY YAMASHITA
Insulation 7/14/2021 Approved MICKEY YAMASHITA
PLUMBING-Rough 7/14/2021 Approved MICKEY YAMASHITA
Interior/Exterior Lathing 7/19/2021 Corrections Issued MICKEY YAMASHITA
Interior/Exterior Lathing 7/21/2021 Approved MICKEY YAMASHITA
Final 8/23/2021 Corrections Issued MICKEY YAMASHITA
Green Building Final 8/23/2021 Approved MICKEY YAMASHITA
SGSOV-Seismic Gas S/O Valve 8/23/2021 SGSOV Approved MICKEY YAMASHITA
Smoke Detectors 8/23/2021 Approved MICKEY YAMASHITA
Final 8/26/2021 OK to Issue CofO MICKEY YAMASHITA