14203 W GAIN ST 91331
Certificate Information: 14203 W GAIN ST 91331
- Application / Permit
- 20016-10000-29741
- Plan Check / Job No.
- B20LA21297
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert Existing detached garage to an Accessory dwelling unit per LAMC 12.22A.33(b)(5)
- Permit Issued
- Issued on 3/19/2021
- Issuing Office
- Current Status
- CofO Issued on 7/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/19/2020 | JOE VO |
| Corrections Issued | 11/19/2020 | JOE VO |
| Applicant returned to address corrections | 2/13/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 3/15/2021 | MONICA RAMIREZ |
| Issued | 3/19/2021 | APPLICANT |
| CofO in Progress | 6/24/2022 | MICKEY YAMASHITA |
| CofO in Progress | 6/24/2022 | MICKEY YAMASHITA |
| CofO Issued | 7/28/2022 | DAVID JAMES |
| Permit Finaled | 7/28/2022 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/3/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2020 | ABDULLAH SADOZAI |
| Construction near power lines | Cleared | 2/4/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/5/2021 | Corrections Issued | MICKEY YAMASHITA |
| HVAC-Rough | 4/5/2021 | Corrections Issued | MICKEY YAMASHITA |
| PLUMBING-Rough | 4/5/2021 | Corrections Issued | MICKEY YAMASHITA |
| Pre-Inspection | 4/5/2021 | Corrections Issued | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 5/27/2021 | Corrections Issued | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 5/27/2021 | Corrections Issued | MICKEY YAMASHITA |
| Green Building Rough | 5/27/2021 | Not Ready for Inspection | MICKEY YAMASHITA |
| PLUMBING-Rough | 5/27/2021 | Corrections Issued | MICKEY YAMASHITA |
| Shower Pan | 5/27/2021 | Approved | MICKEY YAMASHITA |
| ELECTRICAL-Rough | 6/10/2021 | Corrections Issued | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 6/10/2021 | Approved | MICKEY YAMASHITA |
| Gas Test | 6/10/2021 | Partial Approval | MICKEY YAMASHITA |
| HVAC-Rough | 6/10/2021 | Corrections Issued | MICKEY YAMASHITA |
| PLUMBING-Rough | 6/10/2021 | Corrections Issued | MICKEY YAMASHITA |
| Sewer | 6/10/2021 | Corrections Issued | MICKEY YAMASHITA |
| Smoke Detectors | 6/10/2021 | Not Ready for Inspection | MICKEY YAMASHITA |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2021 | Corrections Issued | MICKEY YAMASHITA |
| PLUMBING-Rough | 7/6/2021 | Approved | MICKEY YAMASHITA |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2021 | Corrections Issued | MICKEY YAMASHITA |
| Green Building Rough | 7/12/2021 | Corrections Issued | MICKEY YAMASHITA |
| HVAC-Rough | 7/12/2021 | Corrections Issued | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 7/14/2021 | Approved | MICKEY YAMASHITA |
| ELECTRICAL-Rough | 7/14/2021 | Approved | MICKEY YAMASHITA |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2021 | Approved | MICKEY YAMASHITA |
| Green Building Rough | 7/14/2021 | Approved | MICKEY YAMASHITA |
| HVAC-Rough | 7/14/2021 | Approved | MICKEY YAMASHITA |
| Insulation | 7/14/2021 | Approved | MICKEY YAMASHITA |
| PLUMBING-Rough | 7/14/2021 | Approved | MICKEY YAMASHITA |
| Interior/Exterior Lathing | 7/19/2021 | Corrections Issued | MICKEY YAMASHITA |
| Interior/Exterior Lathing | 7/21/2021 | Approved | MICKEY YAMASHITA |
| Final | 8/23/2021 | Corrections Issued | MICKEY YAMASHITA |
| Green Building Final | 8/23/2021 | Approved | MICKEY YAMASHITA |
| SGSOV-Seismic Gas S/O Valve | 8/23/2021 | SGSOV Approved | MICKEY YAMASHITA |
| Smoke Detectors | 8/23/2021 | Approved | MICKEY YAMASHITA |
| Final | 8/26/2021 | OK to Issue CofO | MICKEY YAMASHITA |