Application / Permit
20016-10000-29724
Plan Check / Job No.
B20LA21287
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft-Story seismic retrofit per LABC Chapter 93: USING 3 SCC SYSTEM, AND DRAG SYSTEM.
Permit Issued
Issued on 4/28/2021
Issuing Office
Current Status
CofC Issued on 3/30/2022

Permit Application Status History

Submitted 11/17/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 JESSE VIDUYA
Corrections Issued 12/16/2020 JESSE VIDUYA
Quality Review Completed 12/21/2020 HANS SANTIAGO
Applicant returned to address corrections 2/10/2021 JESSE VIDUYA
Applicant returned to address corrections 3/2/2021 JESSE VIDUYA
Plan Check Approved 3/10/2021 JESSE VIDUYA
Issued 4/28/2021 APPLICANT
OK for CofC 3/30/2022 DARRYL ARNOLD
CofC Issued 3/30/2022 WINSTON DUNNING

Permit Application Clearance Information

Tenant Habitability Plan Cleared 4/27/2021 MICHAEL SOTO

Contact Information

Contractor Zebra Construction Inc; Lic. No.: 1055609-B       ,
Engineer Tajvidi,, Seyed Mohammad; Lic. No.: NA84559       ,

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/15/2021 Conditional Approval BRUCE CAMPBELL
Excavation/Setback/Form/Re-Bar 1/18/2022 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 1/18/2022 Conditional Approval DARRYL ARNOLD
Structural Steel Frame 1/18/2022 Conditional Approval DARRYL ARNOLD
Wood Frame 1/18/2022 Conditional Approval DARRYL ARNOLD
Deputy Drilled-In Anchors 1/19/2022 Conditional Approval BRUCE CAMPBELL
Interior/Exterior Lathing 2/1/2022 Conditional Approval DARRYL ARNOLD
Final 2/2/2022 Not Ready for Inspection DARRYL ARNOLD
METHANE-Final 2/2/2022 Conditional Approval DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 2/2/2022 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 2/2/2022 Not Ready for Inspection DARRYL ARNOLD
Final 3/2/2022 Not Ready for Inspection DARRYL ARNOLD
METHANE-Final 3/2/2022 Conditional Approval DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 3/2/2022 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 3/2/2022 Conditional Approval DARRYL ARNOLD
Final 3/24/2022 Not Ready for Inspection DARRYL ARNOLD
METHANE-Final 3/24/2022 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 3/24/2022 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 3/24/2022 Approved DARRYL ARNOLD
Final 3/30/2022 OK for CofC DARRYL ARNOLD
METHANE-Final 3/30/2022 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 3/30/2022 SGSOV Approved DARRYL ARNOLD