6082 W CASHIO ST 90035
Certificate Information: 6082 W CASHIO ST 90035
- Application / Permit
- 20016-10000-29724
- Plan Check / Job No.
- B20LA21287
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: USING 3 SCC SYSTEM, AND DRAG SYSTEM.
- Permit Issued
- Issued on 4/28/2021
- Issuing Office
- Current Status
- CofC Issued on 3/30/2022
Permit Application Status History
| Submitted | 11/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | JESSE VIDUYA |
| Corrections Issued | 12/16/2020 | JESSE VIDUYA |
| Quality Review Completed | 12/21/2020 | HANS SANTIAGO |
| Applicant returned to address corrections | 2/10/2021 | JESSE VIDUYA |
| Applicant returned to address corrections | 3/2/2021 | JESSE VIDUYA |
| Plan Check Approved | 3/10/2021 | JESSE VIDUYA |
| Issued | 4/28/2021 | APPLICANT |
| OK for CofC | 3/30/2022 | DARRYL ARNOLD |
| CofC Issued | 3/30/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 4/27/2021 | MICHAEL SOTO |
Contact Information
| Contractor | Zebra Construction Inc; Lic. No.: 1055609-B | , |
| Engineer | Tajvidi,, Seyed Mohammad; Lic. No.: NA84559 | , |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/15/2021 | Conditional Approval | BRUCE CAMPBELL |
| Excavation/Setback/Form/Re-Bar | 1/18/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 1/18/2022 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 1/18/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 1/18/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 1/19/2022 | Conditional Approval | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 2/1/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 2/2/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 2/2/2022 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 2/2/2022 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 2/2/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 3/2/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 3/2/2022 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 3/2/2022 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 3/2/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 3/24/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 3/24/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 3/24/2022 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 3/24/2022 | Approved | DARRYL ARNOLD |
| Final | 3/30/2022 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 3/30/2022 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 3/30/2022 | SGSOV Approved | DARRYL ARNOLD |