4212-4214 S COMPTON AVE 90011
Certificate Information: 4212-4214 S COMPTON AVE 90011
- Application / Permit
- 20016-10000-29493
- Plan Check / Job No.
- B20LA21209
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- TWO ADDITIONS TO ONE-STORY DUPLEX: REAR ADDITION [17'x 24'-6"] AND [4' X 24'-6"] ADDITION OF FRONT PORCH WITH INTERIOR REMODEL & RE-ROOFING.
- Permit Issued
- Issued on 6/1/2022
- Issuing Office
- Metro
- Current Status
- Issued on 6/1/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/14/2020 | JESSE JIMENEZ |
| Corrections Issued | 12/16/2020 | JESSE JIMENEZ |
| Applicant returned to address corrections | 1/28/2021 | SINA KHOSRAVI |
| Building Plans Picked Up | 7/30/2021 | APPLICANT |
| Plan Check Approved | 5/10/2022 | RICARDO RAMIREZ |
| Issued | 6/1/2022 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/12/2021 | JEANIE LAM |
| Sewer availability | Cleared | 1/12/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2021 | JEANIE LAM |
| Tenant Habitability Plan | Cleared | 5/5/2022 | ISMAEL HERNANDEZ |
Contact Information
| Architect | Deenihan,, John Gilmore; Lic. No.: C9147 | 5931 OAKDALE AVENUE WOODLAND HILLS, CA 91367 |
| Contractor | Lee Bobby Ray; Lic. No.: 895263-B | 1420 W 179TH ST #L GARDENA, CA 90248 |
| Engineer | Baich,, Brendon Chad; Lic. No.: C83347 | 1898 WILDROSE AVE POMONA, CA 91767 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Insulation | 6/10/2026 |
Inspection Request History
| Pre-Inspection | 1/9/2023 | Corrections Issued | BRENDAN MORELLI |
| Pre-Inspection | 1/10/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Footing/Foundation/Slab | 2/6/2023 | Corrections Issued | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 2/8/2023 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 2/13/2023 | Partial Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 12/5/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 12/5/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 12/5/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 12/5/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 1/30/2025 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 1/30/2025 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2025 | Corrections Issued | JOHN QUINTANILLA |
| Deputy Wood Construction | 5/12/2025 | Conditional Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 5/30/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 5/30/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 5/30/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Rough-Elec/Plmb/HVAC | 6/6/2025 | Not Ready for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Rough | 6/9/2025 | Conditional Approval | LUIS CASTRO |
| HVAC-Rough | 6/9/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 6/9/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2025 | Partial Approval | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 8/12/2025 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2025 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 9/9/2025 | Not Ready for Inspection | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 9/10/2025 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 9/10/2025 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 11/20/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/14/2026 | Corrections Issued | SABAS ALONSO |
| Green Building Rough | 5/14/2026 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/20/2026 | Approved | ALIZAH MAYAGOITIA |