13809 S FIGUEROA ST 90061

Certificate Information: 13809 S FIGUEROA ST 90061

Application / Permit
20016-10000-29453
Plan Check / Job No.
B20LA21194
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
New breakroom, offices and restrooms in existing warehouse building. Minor exterior upgrade for disabled accessibility. (1979SP60582). NEW SUPPORTS FOR HVAC SYSTEM. * SEPARATE PERMIT FOR NEW EXTERIOR WALL OPENING AND SITE RET. WALLS *
Permit Issued
Issued on 3/25/2021
Issuing Office
Current Status
Issued on 3/25/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/17/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 JOE VO
Corrections Issued 12/31/2020 JOE VO
Quality Review Completed 1/20/2021 MINYE PAK
Plan Check Approved 3/9/2021 JOE VO
Issued 3/25/2021 APPLICANT

Permit Application Clearance Information

DAS Clearance Cleared 3/9/2021 JOE VO
Green Code Cleared 3/9/2021 JOE VO

Contact Information

Architect Wood,, Gregory Desmond; Lic. No.: C12980 8611 SALT LAKE DRIVE      HUNTINGTON BEACH, CA 92646
Contractor Wilson Norm & Sons Inc; Lic. No.: 435700-B       ,

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/1/2021 Approved JOEY BUCHANAN
Footing/Foundation/Slab 4/1/2021 Partial Approval JOEY BUCHANAN
Wood Frame 4/1/2021 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 4/28/2021 Approved JOEY BUCHANAN
Drywall Nailing 5/11/2021 Approved NICK LAROCCA
T-Bar Ceiling 5/27/2021 Approved JOEY BUCHANAN
Final 7/14/2021 Corrections Issued JOEY BUCHANAN
Green Building Final 7/14/2021 Approved JOEY BUCHANAN
Green Building Rough 7/14/2021 Approved JOEY BUCHANAN
METHANE-Final 7/14/2021 Approved JOEY BUCHANAN
METHANE-Rough 7/14/2021 Approved JOEY BUCHANAN
Reinforced Masonry Frame 7/14/2021 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 7/14/2021 SGSOV No Gas JOEY BUCHANAN
Smoke Detectors 7/14/2021 Approved JOEY BUCHANAN
Final 8/23/2021 Corrections Issued JOEY BUCHANAN
Final 10/13/2021 Not Ready for Inspection JOEY BUCHANAN