4954 N HELLMAN AVE 90042
Certificate Information: 4954 N HELLMAN AVE 90042
- Application / Permit
- 20016-10000-29442
- Plan Check / Job No.
- B20LA21184
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EX. LOWER LEVEL OF THREE STORY DWELLING TO AN ADU (696 sf)
- Permit Issued
- Issued on 4/26/2021
- Issuing Office
- Current Status
- CofO Issued on 2/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2020 | RICARDO RAMIREZ |
| Corrections Issued | 11/28/2020 | RICARDO RAMIREZ |
| Building Plans Picked Up | 12/7/2020 | APPLICANT |
| Plan Check Approved | 4/26/2021 | TEODORO DIAZ RODRIGUEZ |
| Issued | 4/26/2021 | APPLICANT |
| CofO in Progress | 2/3/2022 | OSVALDO PARAMO |
| CofO in Progress | 2/3/2022 | OSVALDO PARAMO |
| Permit Finaled | 2/14/2022 | DEROLD HAUFF |
| CofO Issued | 2/14/2022 | DEROLD HAUFF |
| Permit Finaled | 2/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/18/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 1/6/2021 | MATTHEW CRAIG |
| "D" conditions | Cleared | 1/19/2021 | RUBEN VASQUEZ |
| "Q" conditions | Cleared | 1/19/2021 | RUBEN VASQUEZ |
| ZI | Cleared | 1/19/2021 | RUBEN VASQUEZ |
| Sewer availability | Cleared | 4/7/2021 | CECILIO NAVARRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 8/10/2021 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 8/10/2021 | Partial Approval | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2021 | Approved | COREY HUPP |
| Insulation | 8/24/2021 | Approved | COREY HUPP |
| Rough-Elec/Plmb/HVAC | 8/24/2021 | Approved | COREY HUPP |
| Drywall Nailing | 9/27/2021 | Approved | RUBEN SALAS |
| BUILDING-Rough-Frame | 1/12/2022 | Approved | COREY HUPP |
| Final | 1/12/2022 | Corrections Issued | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 1/12/2022 | SGSOV Approved | COREY HUPP |
| Smoke Detectors | 1/12/2022 | Approved | COREY HUPP |
| Final | 1/27/2022 | Conditional Approval | OSVALDO PARAMO |
| Final | 2/2/2022 | OK to Issue CofO | OSVALDO PARAMO |