1300 E PLAZA DEL SOL 90033

Certificate Information: 1300 E PLAZA DEL SOL 90033

Application / Permit
20016-10000-29408
Plan Check / Job No.
B20LA21167
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(14) Community Center operated by governmental agency
Work Description
INTERIOR REMODEL OF EXISTING COMMUNITY BUILDING (ACCESSORY TO BLDG RESIDENTIAL USE A3/B). DEMO OF NON BEARING WALLS CONSTRUCTION OF NON BEARING WALLS, REPLACEMENT OF EXISTING PLUMBING FIXTURES AND FINISHES.
Permit Issued
Issued on 8/11/2021
Issuing Office
Current Status
Permit Finaled on 6/7/2023

Permit Application Status History

Submitted 11/13/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 HERNAN ARREOLA
Corrections Issued 12/12/2020 HERNAN ARREOLA
Disabled Access Plans Picked Up 12/16/2020 APPLICANT
Quality Review Completed 12/17/2020 ALLEN MANALANSAN
Applicant returned to address corrections 1/25/2021 HERNAN ARREOLA
Plan Check Approved 3/21/2021 HERNAN ARREOLA
Issued 8/11/2021 APPLICANT
Building Plans Picked Up 8/18/2021 APPLICANT
Permit Finaled 6/5/2023 RONALD JIMENEZ

Permit Application Clearance Information

Tenant Habitability Plan Cleared 1/26/2021 RICHARD BRINSON
City owned building/parcel Cleared 1/29/2021 DANIEL TARICA
Public Housing Cleared 2/8/2021 JORGE ALCANTAR
DAS Clearance Cleared 2/18/2021 SHINE LIN

Contact Information

Contractor Portrait Construction Inc; Lic. No.: 977636-B 265 N JOY STREET #200      CORONA, CA 92879
Engineer Houshmand,, Mohsen; Lic. No.: C42283 4143 COSTERO RISCO      SAN CLEMENTE, CA 92673

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 3/28/2023 Partial Approval JULIAN CAPUCETTI
Drywall Nailing 4/3/2023 Approved JULIAN CAPUCETTI
T-Bar Ceiling 4/25/2023 Corrections Issued RAFAEL CORTES
T-Bar Ceiling 4/27/2023 Approved JULIAN CAPUCETTI
Pre-Inspection 5/15/2023 Approved JULIAN CAPUCETTI
SGSOV-Seismic Gas S/O Valve 5/30/2023 SGSOV Not Ready JULIAN CAPUCETTI
Final 6/1/2023 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Final 6/1/2023 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 6/1/2023 SGSOV Approved RAMAZANALI ALMASI
Smoke Detectors 6/1/2023 Approved RAMAZANALI ALMASI
Final 6/2/2023 Corrections Issued RONALD JIMENEZ
Final 6/5/2023 Permit Finaled RONALD JIMENEZ
Green Building Final 6/5/2023 Approved RONALD JIMENEZ