10606-10608 W JIMENEZ ST 91342
Certificate Information: 10606-10608 W JIMENEZ ST 91342
- Application / Permit
- 20016-10000-29336
- Plan Check / Job No.
- B20LA21074
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN : CONVERSION OF ATTACHED PLAYROOM AND BREEZEWAY TO AN ATTACHED ACCESSORY DWELLING UNIT PER LAMC A.33(B)(5)
- Permit Issued
- Issued on 5/12/2021
- Issuing Office
- Current Status
- CofO Issued on 1/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2020 | MONICA RAMIREZ |
| Corrections Issued | 11/18/2020 | MONICA RAMIREZ |
| Applicant returned to address corrections | 4/29/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 5/3/2021 | MONICA RAMIREZ |
| Plan Check Approved | 5/5/2021 | MONICA RAMIREZ |
| Issued | 5/12/2021 | APPLICANT |
| CofO in Progress | 11/17/2021 | MATTHEW NELSON |
| CofO Issued | 1/15/2022 | MICHAEL SMITH |
| Permit Finaled | 1/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/16/2021 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 2/16/2021 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2021 | MARKOS PEREZ-BRAN |
| Grading Pre-Inspection | Cleared | 5/4/2021 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/27/2021 | Approved | MATTHEW NELSON |
| Sewer | 6/17/2021 | Partial Approval | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 6/21/2021 | No Access for Inspection | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 6/23/2021 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 6/23/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/20/2021 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 7/20/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 7/20/2021 | Corrections Issued | MATTHEW NELSON |
| Insulation | 7/20/2021 | Partial Inspection | MATTHEW NELSON |
| MERV13>=Rough | 7/20/2021 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 7/20/2021 | Approved | MATTHEW NELSON |
| Wood Frame | 7/20/2021 | Partial Approval | MATTHEW NELSON |
| HVAC-Rough | 8/6/2021 | Approved | MATTHEW NELSON |
| Insulation | 8/6/2021 | Approved | MATTHEW NELSON |
| Wood Frame | 8/6/2021 | Approved | MATTHEW NELSON |
| Drywall Nailing | 8/20/2021 | Approved | MATTHEW NELSON |
| Insulation | 8/20/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/20/2021 | Approved | MATTHEW NELSON |
| Masonry Wall/Backfill | 8/20/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Drywall Nailing | 8/23/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/23/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/22/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 10/22/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 10/22/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 10/22/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| MERV13>=Final | 10/22/2021 | Approved | CHRISTOPHER DELLEFIELD |
| MERV13>=Rough | 10/22/2021 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 10/22/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 10/22/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 11/3/2021 | No Access for Inspection | MATTHEW NELSON |
| Final | 11/5/2021 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Final | 11/17/2021 | Approved | MATTHEW NELSON |
| Final | 11/17/2021 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 11/17/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 11/17/2021 | Approved | MATTHEW NELSON |