1216 N WILCOX AVE 90038

Certificate Information: 1216 N WILCOX AVE 90038

Application / Permit
20016-10000-29333
Plan Check / Job No.
B20LA21072
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePlan* Convert (E) Recreation room to a (N) Accessory Dwelling Unit per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 2/17/2021
Issuing Office
Current Status
Issued on 2/17/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/12/2020 APPLICANT
Assigned to Plan Check Engineer 11/17/2020 CARLOS MONTES
Corrections Issued 11/17/2020 CARLOS MONTES
Applicant returned to address corrections 12/2/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 12/17/2020 CARLOS MONTES
Applicant returned to address corrections 12/30/2020 HELEN NGUYEN
Applicant returned to address corrections 1/24/2021 ARSALAN SHABESTARI
Applicant returned to address corrections 2/9/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 2/11/2021 CRYSTEL MAALOUF
Plan Check Approved 2/17/2021 LAMAR DAVIS
Issued 2/17/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/25/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 11/25/2020 JEANIE LAM
Sewer availability Cleared 11/25/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 11/30/2020 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/24/2021 Corrections Issued BRIAN SULLIVAN
Pre-Inspection 3/8/2021 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 3/17/2021 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 3/17/2021 Approved BRIAN SULLIVAN
Green Building Rough 3/17/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 3/17/2021 Approved BRIAN SULLIVAN
PLUMBING-Rough 3/17/2021 Approved BRIAN SULLIVAN
Drywall Nailing 3/25/2021 Approved BRIAN SULLIVAN
Final 3/30/2021 Corrections Issued RAUL BARAJAS
Green Building Final 3/30/2021 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 3/30/2021 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 3/30/2021 Not Ready for Inspection RAUL BARAJAS
Final 4/1/2021 Corrections Issued RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 4/1/2021 SGSOV Approved RAUL BARAJAS
Smoke Detectors 4/1/2021 Approved RAUL BARAJAS