8909 W GIBSON ST 90034
Certificate Information: 8909 W GIBSON ST 90034
- Application / Permit
- 20016-10000-29178
- Plan Check / Job No.
- B20LA21035
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED RECREATION ROOM TO ADU PER GCS65852.2(e)(1)(A
- Permit Issued
- Issued on 10/27/2021
- Issuing Office
- Current Status
- CofO Issued on 7/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 12/5/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 1/28/2021 | ADAM HEGAZI |
| Plan Check Approved | 7/29/2021 | RICARDO RAMIREZ |
| Issued | 10/27/2021 | APPLICANT |
| Building Plans Picked Up | 11/2/2021 | APPLICANT |
| CofO in Progress | 7/21/2022 | EVAN COOPER |
| Permit Finaled | 7/29/2022 | DANIEL ORRANTE |
| CofO Issued | 7/29/2022 | DANIEL ORRANTE |
| Permit Finaled | 7/29/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/21/2021 | THOMAS LANG |
| Sewer availability | Cleared | 1/21/2021 | THOMAS LANG |
| Construction near power lines | Cleared | 3/31/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2021 | MSTAFA AL-MSARI |
Contact Information
| Architect | Herron,, Elizabeth Anne; Lic. No.: C15167 | 935 W AVE 37 LOS ANGELES, CA 900653241 |
| Contractor | Owner-Builder | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Final | 5/5/2022 | Corrections Issued | EVAN COOPER |
| Final | 5/5/2022 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 5/5/2022 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 5/5/2022 | Corrections Issued | EVAN COOPER |
| Smoke Detectors | 5/5/2022 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 6/9/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/23/2022 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 7/20/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 7/20/2022 | Approved | EVAN COOPER |
| Final | 7/20/2022 | OK to Issue CofO | EVAN COOPER |
| HVAC-Final | 7/20/2022 | Approved | EVAN COOPER |
| PLUMBING-Final | 7/20/2022 | Approved | EVAN COOPER |
| Smoke Detectors | 7/20/2022 | Approved | EVAN COOPER |