18038 W BLUE SAIL DR 90272

Certificate Information: 18038 W BLUE SAIL DR 90272

Application / Permit
20016-10000-29138
Plan Check / Job No.
B20LA20970
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
KITCHEN REMODEL, NEW FIREPLACE(replace (E)), (2) NEW SLIDING DOOR IN BEDROOMS, REPLACE ENTRY DOOR.
Permit Issued
Issued on 8/20/2021
Issuing Office
Current Status
Permit Finaled on 9/25/2023

Permit Application Status History

Submitted 11/12/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 TSE MING HUANG
Corrections Issued 1/19/2021 TSE MING HUANG
Applicant returned to address corrections 3/4/2021 TSE MING HUANG
Applicant returned to address corrections 3/27/2021 LAWRENCE QUIRANTE
Building Plans Picked Up 4/23/2021 APPLICANT
Applicant returned to address corrections 7/16/2021 LUKE GONZALES
Applicant returned to address corrections 7/22/2021 LUKE GONZALES
Plan Check Approved 8/5/2021 LUKE GONZALES
Plan Check Approved 8/20/2021 LUKE GONZALES
Issued 8/20/2021 APPLICANT
Permit Finaled 9/25/2023 ARAM AVEDISIAN

Permit Application Clearance Information

Coastal Zone Cleared 1/22/2021 ANACANY HURTADO
ZI Cleared 1/22/2021 ANACANY HURTADO
Grading Pre-Inspection Cleared 2/22/2021 KIRK LINKLATER

Contact Information

Contractor B C Construction; Lic. No.: 676747-B 1137 EAST 46TH STREET      LONG BEACH, CA 90807
Engineer Finley,, Lawrence Rufus; Lic. No.: C46606 1178 E 9TH ST      LONG BEACH, CA 90813

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 12/15/2021 Not Ready for Inspection JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 12/15/2021 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 12/15/2021 Not Ready for Inspection JOHN KIDWELL
Structural Steel Frame 12/15/2021 Not Ready for Inspection JOHN KIDWELL
Wood Frame 12/15/2021 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 3/1/2022 Approved ANDREW NAVE
ELECTRICAL-Rough 3/1/2022 Not Ready for Inspection ANDREW NAVE
PLUMBING-Rough 3/1/2022 Approved ANDREW NAVE
ELECTRICAL-Rough 3/14/2022 Approved ANDREW NAVE
Interior/Exterior Lathing 3/14/2022 Partial Approval ANDREW NAVE
Interior/Exterior Lathing 4/26/2022 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 4/27/2022 Approved ANDREW NAVE
Shower Pan 4/27/2022 Approved ANDREW NAVE
Final 9/25/2023 Permit Finaled ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 9/25/2023 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 9/25/2023 Approved ARAM AVEDISIAN