121 N GAFFEY ST 90731
Certificate Information: 121 N GAFFEY ST 90731
- Application / Permit
- 20016-10000-29008
- Plan Check / Job No.
- B20LA20894
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- REMODEL OF EXISTING RESTAURANT WITH OUT DOOR DINING AREA.
- Permit Issued
- Issued on 11/1/2021
- Issuing Office
- Current Status
- CofO Issued on 8/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2020 | LAWRENCE QUIRANTE |
| Corrections Issued | 12/3/2020 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 3/10/2021 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 4/27/2021 | RICARDO RAMIREZ |
| Plan Check Approved | 8/19/2021 | ADAM HEGAZI |
| Issued | 11/1/2021 | APPLICANT |
| Building Plans Picked Up | 11/4/2021 | APPLICANT |
| TCO Issued (Expire Date: 07-10-2023) | 1/11/2023 | DAVID TSAU |
| CofO in Progress | 8/3/2023 | JOEY BUCHANAN |
| Permit Finaled | 8/3/2023 | DAVID TSAU |
| CofO Issued | 8/3/2023 | DAVID TSAU |
| Permit Finaled | 8/3/2023 | DAVID TSAU |
Permit Application Clearance Information
| Comm Cor/Mini-Mall | Cleared | 6/1/2021 | RICHARD REASER |
| Redevelopment Project Area | Cleared | 7/12/2021 | DAVID URITA |
| Grading Pre-Inspection | Cleared | 7/22/2021 | TIMOTHY POWELL |
| Community Plan Implem. Overlay | Cleared | 8/12/2021 | JEANALEE OBERGFELL |
| Food establishment approval | Cleared | 8/19/2021 | LACDHS APPROVED |
Contact Information
| Architect | Neiss,, Scott Martin; Lic. No.: C24089 | 35318 N 31ST DRIVE PHOENIX, AZ 85086 |
| Contractor | Jungsco Inc; Lic. No.: 951264-B | 1885 COMMONWEALTH AVE_UNIT B FULLERTON, CA 92833 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/3/2021 | Approved | NICK LAROCCA |
| Footing/Foundation/Slab | 12/3/2021 | Not Ready for Inspection | NICK LAROCCA |
| Footing/Foundation/Slab | 12/6/2021 | Partial Approval | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 12/23/2021 | Approved | JOEY BUCHANAN |
| Light Gage Steel Frame | 2/9/2022 | Partial Approval | JOEY BUCHANAN |
| Wood Frame | 3/11/2022 | Partial Approval | JOEY BUCHANAN |
| Drywall Nailing | 4/27/2022 | Approved | JOEY BUCHANAN |
| Insulation | 4/27/2022 | Approved | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2022 | Corrections Issued | DAVID TSAU |
| Wood Frame | 5/16/2022 | Partial Approval | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2022 | Approved | JOEY BUCHANAN |
| Wood Frame | 5/25/2022 | Partial Approval | JOEY BUCHANAN |
| Wood Frame | 6/3/2022 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 6/9/2022 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 6/13/2022 | Partial Approval | JOEY BUCHANAN |
| Interior/Exterior Lathing | 7/6/2022 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 9/21/2022 | Approved | JOEY BUCHANAN |
| T-Bar Ceiling | 10/4/2022 | Conditional Approval | JOEY BUCHANAN |
| T-Bar Ceiling | 10/6/2022 | Approved | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 10/12/2022 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 10/12/2022 | Approved | JOEY BUCHANAN |
| Final | 11/22/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Pre-Inspection | 11/22/2022 | Approved | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 11/22/2022 | Approved | JOEY BUCHANAN |
| Pre-Inspection | 12/23/2022 | Approved | JOEY BUCHANAN |
| Special/Order Compliance | 12/23/2022 | Corrections Issued | JOEY BUCHANAN |
| T-Bar Ceiling | 12/23/2022 | Approved | JOEY BUCHANAN |
| Final | 1/9/2023 | OK for TCO | JOEY BUCHANAN |
| Special/Order Compliance | 6/14/2023 | Partial Inspection | AMANUEL BERHE |