4368 N FORMAN AVE 91602

Certificate Information: 4368 N FORMAN AVE 91602

Application / Permit
20016-10000-29007
Plan Check / Job No.
B20LA20893
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE AND RECREATION ROOM INTO ACCESSORY DWELLING UNIT PER WFPP (CONVERSTION OF ACCESSORY BUILDING PER STATE LAW)
Permit Issued
Issued on 2/22/2021
Issuing Office
Current Status
CofO Issued on 8/28/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/10/2020 APPLICANT
Assigned to Plan Check Engineer 11/25/2020 AUNG SOE
Corrections Issued 11/30/2020 AUNG SOE
Plan Check Approved 2/16/2021 GEORGE ALVAREZ
Issued 2/22/2021 APPLICANT
Building Plans Picked Up 2/24/2021 APPLICANT
CofO in Progress 7/20/2021 THOMAS FINNILA
CofO Issued 8/28/2021 MICHAEL SMITH
Permit Finaled 8/28/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/20/2021 GABRIEL ROBLES
Sewer availability Cleared 1/20/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 1/21/2021 GABRIEL ROBLES
ZI Cleared 2/4/2021 RUBEN VASQUEZ

Contact Information

Contractor Flip It Homes Inc; Lic. No.: 1043456-B 20501 VENTURA BLVD #135      WOODLAND HILLS, CA 91364

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/1/2021 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 4/1/2021 Partial Approval THOMAS FINNILA
Sewer 4/1/2021 Approved THOMAS FINNILA
Footing/Foundation/Slab 4/9/2021 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 4/27/2021 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 4/27/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 4/27/2021 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 5/4/2021 Approved THOMAS FINNILA
PLUMBING-Rough 5/4/2021 Approved THOMAS FINNILA
Pre-Inspection 5/4/2021 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 5/11/2021 Conditional Approval THOMAS FINNILA
Insulation 5/11/2021 Approved THOMAS FINNILA
Interior/Exterior Lathing 5/11/2021 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 5/19/2021 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 5/20/2021 Approved THOMAS FINNILA
Drywall Nailing 5/24/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 5/28/2021 Not Ready for Inspection THOMAS FINNILA
Shower Pan 5/28/2021 Approved THOMAS FINNILA
Interior/Exterior Lathing 6/7/2021 Approved DANIEL ORRANTE
SGSOV-Seismic Gas S/O Valve 6/25/2021 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 6/25/2021 Not Ready for Inspection THOMAS FINNILA
Final 7/6/2021 Partial Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 7/6/2021 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 7/6/2021 Approved THOMAS FINNILA
ELECTRICAL-Final 7/9/2021 Approved MICHEL ABAJAN
HVAC-Final 7/9/2021 Approved MICHEL ABAJAN
PLUMBING-Final 7/9/2021 Approved MICHEL ABAJAN
Pre-Inspection 7/9/2021 Approved MICHEL ABAJAN
Final 7/20/2021 OK to Issue CofO THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 7/20/2021 SGSOV Approved THOMAS FINNILA